Vertical Air Terminal Installation - Napoleon BGD36CFNTR Installation And Operating Instructions Manual

Table of Contents

Advertisement

4.4.2 VERTICAL AIR TERMINAL INSTALLATION

IF USING CLAMPS TO CONNECT VENT COMPONENTS, 3 SCREWS MUST ALSO BE USED TO EN-
MAINTAIN A MINIMUM 2" SPACE BETWEEN THE AIR INLET BASE AND THE STORM COLLAR.
RISK OF FIRE, EXPLOSION OR ASPHYXIATION. IMPROPER SUPPORT OF THE ENTIRE VENTING
SYSTEM MAY ALLOW VENT TO SAG AND SEPARATE. USE VENT RUN SUPPORTS AND CONNECT
A.
Fasten the roof support to the roof using the screws provided. The
roof support is optional. In this case the venting is to be adequately
supported using either an alternate method suitable to the authority
having jurisdiction or the optional roof support.
B.
Stretch the inner fl ex pipe to the required length. Slip the
inner fl ex pipe a minimum of 2" over the inner pipe of the air
terminal connector and secure with 3 #8 screws. Seal using
a heavy bead of high temperature sealant W573-0007 (not
supplied).
C.
Repeat using the outer fl ex pipe, using a heavy bead of
high temperature sealant W573-0002 (not supplied).
D.
Thread the air terminal connector / vent pipe assembly down through
the roof. The air terminal must be positioned vertically and plumb.
Attach the air terminal connector to the roof support, ensuring that the
top of the air terminal is 16" above the highest point that it penetrates
the roof.
E.
Remove nails from the shingles, above and to the sides of the air
terminal connector. Place the fl ashing over the air terminal connector
leaving a min. 3/4" of the air terminal connector showing above
the top of the fl ashing. Slide the fl ashing underneath the sides and
upper edge of the shingles. Ensure that the air terminal connector
is properly centred within the fl ashing, giving a 3/4" margin all
around. Fasten to the roof. Do not nail through the lower portion
of the fl ashing. Make weather-tight by sealing with caulking. Where
possible, cover the sides and top edges of the fl ashing with roofi ng
material.
F.
Aligning the seams of the terminal and air terminal connector,
place the terminal over the air terminal connector making sure
the vent pipe goes into the hole in the terminal. Secure with the
three screws provided.
G.
Apply a heavy bead of weatherproof caulking 2" above the
fl ashing. Install the storm collar around the air terminal and slide
down to the caulking. Tighten to ensure that a weather-tight seal
between the air terminal and the collar is achieved.
H.
If more vent pipe needs to be used to reach the appliance see "HORIZONTAL
AIR TERMINAL INSTALLATION" section.
!
SURE THE CONNECTION CANNOT SLIP OFF.
DO NOT CLAMP THE FLEXIBLE VENT PIPE.
VENT SECTIONS PER INSTALLATION INSTRUCTIONS.
WARNING
ROOF SUPPORT
INNER PIPE
AIR
TERMINAL
CONNECTOR
HIGH
TEMPERATURE
SEALANT
INNER FLEX PIPE
OUTER FLEX PIPE
AIR INLET
2"
BASE
CAULKING
STORM COLLAR
WEATHER
SEALANT
FLASHING
24.1
W415-0785 / A / 07.23.09
25

Advertisement

Table of Contents
loading

This manual is also suitable for:

Bgd36cfgpBgd36cfgnBgd36cfptr

Table of Contents