5.
SW Circuit Board
(Time required: About 10 minutes)
5-1
Remove the lower case assembly. (See procedure 1.)
5-2
Remove the two (2) screws marked [340]. The SW circuit
board can then be removed. (Fig. 2)
5-3
Remove the red knob from the SW circuit board.
6.

Tweeter (PSR-1000)

(Time required: About 10 minutes)
6-1
Remove the lower case assembly. (See procedure 1.)
6-2
Remove the two (2) screws marked [270B]. The tweeter
can then be removed. (Fig. 2)
*
The left and right tweeters can be removed in the respectively
same method.
7.

Tweeter (PSR-2000)

(Time required: About 10 minutes)
7-1
Remove the lower case assembly. (See procedure 1.)
7-2
Remove the two (2) screws marked [290]. The tweeter can
then be removed. (Fig. 2)
*
The left and right tweeters can be removed in the respectively
same method.
8.
Woofer (PSR-1000)
(Time required: About 10 minutes)
8-1
Remove the lower case assembly. (See procedure 1.)
8-2
Remove the four (4) screws marked [100A]. The woofer
can then be removed. (Fig. 2)
*
The left and right woofers can be removed in the respectively
same method.
9.

Woofer (PSR-2000)

(Time required: About 10 minutes)
9-1
Remove the lower case assembly. (See procedure 1.)
9-2
Remove the four (4) screws marked [100B]. The woofer and
the four (4) speaker holders can then be removed. (Fig. 2)
*
The left and right woofers can be removed in the respectively
same method.
10.
Floppy Disk Drive
(Time required: About 10 minutes)
10-1
Remove the lower case assembly. (See procedure 1.)
10-2
Remove the four (4) screws marked [50]. The floppy disk
drive assembly can then be removed. (Fig. 2)
10-3
Remove the four (4) screws marked [F40]. The left and right
FDD holders can then be removed from the floppy disk
drive. (Fig. 3)
11.
Keyboard Assembly
(Time required: About 10 minutes)
11-1
Remove the lower case assembly. (See procedure 1.)
11-2
Remove the two (2) screws marked [250B]. The keyboard
assembly can then be removed. (Fig. 2)
12.
INV Circuit Board
(Time required: About 10 minutes)
ATTENTION: High Voltage
12-1
Remove the lower case assembly. (See procedure 1.)
12-2
Remove the four (4) screws marked [260A]. The INV
circuit board can then be removed. (Fig. 2)
13.
DM Circuit Board, Shield Cover L and U
(Time required: About 15 minutes)
13-1
Remove the lower case assembly. (See procedure 1.)
13-2
Remove the INV circuit board. (See procedure 12.)
13-3
Remove the eight (8) screws marked [260B] and the five
(5) screws marked [270C]. The shield cover L can then be
removed. (Fig. 2)
13-4
Remove the four (4) screws marked [260C]. The DM
circuit board can then be removed. (Fig. 4)
13-5
Remove the screw marked [270D]. The shield cover U can
then be removed. (Fig. 4)
Floppy disk drive
[F40]: Bind Head Tapping Screw 3.0x6 MFZN2BL (EG330360)
[260C]
[260C]
[260C]: Bind Head Tapping Screw-B 3.0x6 MFZN2Y (EP600130)
[270D]: Bind Head Tapping Screw-P 3.0x8 MFZN2Y (EP600280)
(Fig. 4)
PSR-1000/PSR-2000
[F40]x4
FDD holder R
(Fig. 3)
[260C]
DM