PROGRAMMING THE BREWER (cont.)
SET NEW RECIPE
Using a Smart Funnel and a G9-2T DBC or MHG
Grinder:
This function allows the operator to set BREW
VOLUMES, BYPASS PERCENTAGES, PULSE BREW
TIMES, and DRIP-OUT TIMES for each coffee name
preset in the grinder's memory.
Certain coffee NAMES are stored in the G9-2T
DBC's memory. When a particular name of coffee is
ground into the Smart Funnel, that name and the batch
size selected are transferred from the grinder to the
programming chip located in the funnel handle. The
funnel is then inserted into the brewer's left side funnel
rails. The sensor coil on the brewer reads the informa-
tion contained in the handle. The name of the coffee
flavor will then appear on the display. This then allows
the operator to set the BREW VOLUMES, BYPASS
PERCENTAGES, PULSE BREW TIMES, and DRIP-OUT
TIMES for that particular coffee NAME. It also allows
the operator to set other brewing parameters, such
as BREW TEMPERATURE, READY TEMPERATURE,
BREW LOCKOUTS, etc. Each coffee NAME can be set
individually to provide optimum brewing quality.
SET NEW RECIPE?
NO
INSERT FUNNEL
WITH NEW NAME
USE LEFT SIDE
QUIT SETUP?
FUNNEL
CONTAINS NAME
(COFFEE NAME)
NO
YES
BEGIN SETUP OF
(COFFEE NAME)
SETUP BREW VOLUMES, BYPASS,
PULSE BREW, PREINFUSION, DRIPOUT TIME
3 BATCHES DONE?
NO
(COFFEE NAME)
SETUP COMPLETE
REVIEW RECIPES?
NO
YES
2 SEC.
CYCLES THROUGH
THREE SCREENS
ONLY
2 SEC.
YES
FUNNEL DETECTED
FUNNEL CONTAINS
NO NAME
MUST GRIND INTO
FUNNEL FIRST
SEE SEPARATE DIAGRAMS
FOR SETUP INSTRUCTIONS
YES
YES
P2299
Procedure for Setting the Recipe:
NOTE: Before beginning setup, place a server beneath
the left brew funnel.
1. Insert the funnel into the grinder and select a batch
size to grind. It is not necessary to have coffee beans
in the hopper(s) in order to program the brewer.
The coffee name is pre-selected and stored in the
grinder's memory for the side being ground.
2. Press the GRIND switch. When the grinder stops
grinding, remove the funnel.
3. On the brewer, press and hold the upper right
hidden switch (®) until the display reads UNITS.
Release the switch, then press switch again until
display reads SET NEW RECIPE.
4. Press and release YES. The display should read
INSERT FUNNEL WITH NEW NAME, then USE
LEFT SIDE ONLY, and finally, QUIT SETUP? These
three displays will repeatedly cycle.
5. Insert the funnel into the rails on the left side of
the brewer. The display should read the NAME of
the coffee that was ground into the funnel, along
with a NO and YES. If the NAME on the display is
correct, press YES.
6. If, for some reason, the name of the coffee from
the grinder did not load properly into the funnel,
or if a grind has not yet been done, the display will
read MUST GRIND INTO FUNNEL FIRST. It will be
necessary to grind another batch following steps
1 and 2.
7. If the grind is acknowledged by the brewer, the
display will read BEGIN SETUP OF (COFFEE NAME).
Then the screen will display BREW OZ. and a batch
light will be blinking. (Refer to BREW OZ (SETTING
OR ADJUSTING for description)
Page 17
BREW OZ. XX.X
(-)
DONE
(+)
3 BATCHES DONE?
NO
YES
% BYPASS XX.X
(-)
DONE
(+)
P2415