Step 1
Carefully remove the ground mount assembly (P/N 208800 - motorizable or P/N
202680-2 manual) from the packing crate. Leave the steel strapping intact to avoid dis-
engagement of the panning frame from the square-tube weldment during the ground
mount installation.
Step 2
Securely attach the crane to the ground mount assembly using a sling, and carefully
raise the entire ground mount as shown in Figure 3-3.
Step 3
Align the ground mount assembly directly over the anchor bolts (P/N 203314 - manual
or P/N 203666 - motorizable), which should have been previously mounted in the foun-
dation pad.
NOTE: Ground mount positioning on the foundation is dependent upon predetermined
azimuth viewing requirements. The ground mount assembly arm should be positioned
opposite the satellite requirement. If your site is in the Northern hemisphere, your satel-
lite will be located in the South. If your site is in the Southern hemisphere, your satellite
will be located in the North.
Step 4
Lower the ground mount assembly onto the anchor bolts with the corresponding hole
pattern.
Figure 3-3: Raising Ground Mount Assembly