Export Edison/Hartford/Hawthorne/Peyton 2-Pump Models (50 Hz)
Voltage:
# of Wires:
Frequency:
Current Draw:
Circuit Breaker:
*
In the 20A configuration, the heater will not operate while either jets pump
is running in high speed. This is the factory setting.
** In the 30A configuration, the heater will not operate while both jets pumps
are running in high speed.
*** In the 40A configuration, the heater will operate while both jets pumps are
running in high speed.
6.0

Electrical Wiring Instructions

IMPORTANT NOTICE: The electrical wiring of this spa
must meet the requirements of the National Electrical Code/
USA (NEC) and any applicable state or local codes. The
electrical circuit must be installed by a qualified electrician
and approved by a local building/electrical inspection authority.
1. Convertible 120/240V Denali/Tacoma Models Only:
DANGER:
!
PRODUCT DAMAGE OR ELECTRICAL FIRE.
120V "Plug-in" Operation: This spa must operate on the supplied 10
feet (3m) 120V GFCI cord at its original length or must be hard-wired
for longer runs. NEVER USE AN EXTENSION CORD FOR ANY
REASON!
Convertible 120/240V Heater Operation: The included 120V GFCI
cord must be discarded for 240V heater operation. This spa must
be hard-wired. Supplying power to either configuration above
which is not in accordance with these instructions will void both the
independent testing agency listing and the manufacturer's warranty.
Page 14
230V/20A*
230 VAC
3
50 Hz
15A
20A
TO DECREASE THE RISK OF SHOCK,
230V/30A**
230 VAC
3
50 Hz
23A
30A
230V/40A***
230 VAC
3
50 Hz
29A
40A