Gas Manifold Pressure Measurement And Adjustment; Gas Input Rate Measurement (Natural Gas Only ) - Amana AMV8 Installation Instructions Manual

Tw-stage gas-fired warm air furnace
Table of Contents

Advertisement

Gas Line
Gas
Shutoff
Valve
Drip Leg Cap
With Fitting
Manometer Hose
Measuring Inlet Gas Pressure (Alt. Method)
NOTE: If measuring gas pressure at the drip leg, a field supplied
hose barb fitting must be installed prior to making the hose
connection. If using the inlet pressure boss on the gas valve,
then use the 36G Valve Pressure Check Kit, Goodman Part No.
0151K00000S.
3. Turn ON the gas supply and operate the furnace and all
other gas consuming appliances on the same gas supply
line.
4. Measure furnace gas supply pressure with burners firing.
Supply pressure must be within the range specified in the
Inlet Gas Supply Pressure table.
Inlet Gas Supply Pressure
Natural Gas
Minimum: 5.0" w.c.
Propane Gas Minimum: 11.0" w.c.
If supply pressure differs from table, make the necessary
adjustments to pressure regulator, gas piping size, etc., and/or
consult with local gas utility.
5. Turn OFF gas to furnace at the manual shutoff valve and
disconnect manometer. Reinstall plug before turning on
gas to furnace.
6. Turn OFF any unnecessary gas appliances stated in step
3.
G
M
P
AS
ANIFOLD
RESSURE
T
O PREVENT UNRELIABLE OPERATION OR EQUIPMENT DAMAGE, THE GAS
MANIFOLD PRESSURE MUST BE AS SPECIFIED ON THE UNIT RATING PLATE.
O
NLY MINOR ADJUSTMENTS SHOULD BE MADE BY ADJUSTING THE GAS VALVE
PRESSURE REGULATOR.
Only small variations in gas pressure should be made by adjusting
the gas valve pressure regulator. The manifold pressure must be
measured with the burners operating. To measure and adjust
the manifold pressure, use the following procedure.
Gas Line
To Furnace
Open To
Atmosphere
Manometer
Maximum:10.0" w.c.
Maximum:13.0" w.c.
M
A
EASUREMENT AND
DJUSTMENT
CAUTION
1. Turn OFF gas to furnace at the manual gas shutoff valve
external to the furnace.
2. Turn off all electrical power to the system.
3. Back outlet pressure test screw (inlet/outlet pressure boss)
out one turn (counterclockwise, not more than one turn).
4. Attach a hose and manometer to the outlet pressure boss
of the valve.
5. Turn ON the gas supply.
6. Turn on power and energize main (M) solenoid. Do not
energize the HI solenoid.
7. Measure gas manifold pressure with burners firing. Adjust
manifold pressure using the Manifold Gas Pressure table
shown below.
8. Remove regulator cover screw from the low (LO) outlet
pressure regulator adjust tower and turn screw clockwise
to increase pressure, or counterclockwise to decrease
pressure.
9. Energize main (M) solenoid as well as the HI terminal.
10. Remove regulator cover screw from the HI outlet pressure
regulator adjust tower and turn screw clockwise to increase
pressure, or counterclockwise to decrease pressure.
11. Turn off all electrical power and gas supply to the system.
12. Remove manometer hose from outlet pressure boss.
13. Turn outlet pressure test screw in to seal pressure port
(clockwise, 7 in-lb minimum).
14. Turn on electrical power and gas supply to the system.
15. Turn on system power and energize valve.
16. Using a leak detection solution or soap suds, check for
leaks at pressure boss screw. Bubbles forming indicate a
leak. SHUT OFF GAS AND FIX ALL LEAKS IMMEDIATELY.
NOTE: For gas to gas conversion, consult your dealer for
appropriate conversion.
M a n i fo l d G a s P re ssu re
G a s
R a te
L o w S t a g e
N a t ura l
H ig h S ta g e
L o w S t a g e
P ro p a n e
H ig h S ta g e
G
I
R
M
AS
NPUT
ATE
EASUREMENT
The gas input rate to the furnace must never be greater than that
specified on the unit rating plate. To measure natural gas input
using the gas meter, use the following procedure.
1. Turn OFF the gas supply to all other gas-burning
appliances except the furnace.
2. While the furnace is operating, time and record one
complete revolution of the smallest gas meter dial.
3. Calculate the number of seconds per cubic foot (sec/ ft
gas being delivered to the furnace. If the dial is a one cubic
foot dial, divide the number of seconds recorded in step 2
by one. If the dial is a two cubic foot dial, divide the number
of seconds recorded in step 2 by two.
4. Calculate the furnace input in BTUs per hour (BTU/ hr).
Input equals the sum of the installation's gas heating value
and a conversion factor (hours to seconds) divided by the
number of seconds per cubic foot. The measured input
must not be greater than the input indicated on the unit
rating plate.
25
R a n g e
N o m i n a l
1 . 6 t o 2 .2 " w . c .
1 . 9 " w . c .
3 . 2 t o 3 .8 " w . c .
3 . 5 " w . c .
5 . 7 t o 6 .3 " w . c .
6 . 0 " w . c .
9 . 7 to 1 0 .3 " w . c . 1 0 . 0 " w . c .
(N
G
O
)
ATURAL
AS
NLY
3
) of