Greenheck Outdoor Air Ventilator Installation, Operation & Maintenance Instructions Manual page 10

Greenheck neutralizer 100% outdoor air ventilator installation, operation and maintenance instructions
Table of Contents

Advertisement

6. Attach Filter/Coil Section
Use a crane and spreader bar hooked to factory
lifting lugs (as shown in diagram) to lift and center the filter section on the NV unit. Note that the top U-
shaped flange on the filter section fits over the vertical flange of the NV unit (see detail A). Use sheet metal
screws to fasten the filter section to NV unit. Mounting holes are prepunched, see diagram for approximate
hole locations.
Filters ship separately. To install, remove side panel on filter section and slide into filter channels. Note
arrows on filters for correct orientation.
Spreader Bar
Lifting Lugs (2)
Detail A
KSU Unit
Filter/Coil Section
(if included)
Note:
If the optional up-stream heating coil
section is included with the unit, special
support for this section is required. See
page 8 for requirements.
Fasten through
both flanges.
Butt units together
10
5. Install Unit.
Use a crane and spreader bar to prevent damage
to unit. Lifting lugs are provided as shown in
illustration.
It is highly recommended that all accessory items
be lifted separately and attached after the unit is
in place.
Electrical and pipe connections can be made at
this time.
Filter /Coil section fastener locations
typical for entire section.
Top fasteners are accessed from
outside, side fasteners are accessed
from inside, bottom fasteners are
accessed from underneath filter section
(Note: bottom fasteners are not required
for slab mounted units).

Advertisement