Complete Shutdown Of A Parallel System - GE Digital Energy LP 33 Series Operating Manual

50 & 60 kva
Hide thumbs Also See for Digital Energy LP 33 Series:
Table of Contents

Advertisement

7.2.6

Complete shutdown of a parallel system

As a result of this procedure the parallel system is completely switched OFF and not powered.
NOTE !
This procedure involves all equipment powered by parallel system, to be shut down.
1.
Perform the command total off on any one of the units.
2.
Switch OFF the output switch Q1 (Pos. 0) on each unit.
3.
Switch OFF battery breaker from battery cabinets of all units.
4.
In order to discharge the DC link capacitors, start once more
the inverter on each unit through the screen:
MENU/COMMAND MENU/INVERTER ON
Remark:
command INVERTER ON will be enabled only when
the inverter voltage of each phase decreases
below 7 VAC (about 30 seconds).
Before proceeding to step 5, check on the display panel that
the DC link voltage (both polarities) Udcp and Udcn has reached
the minimum voltage of 5 VDC (about 30 seconds).
5.
Switch OFF the inverter on each unit entering the screen:
MENU/COMMAND MENU/INVERTER OFF
6.
Switch OFF the mains power of each unit at the AC input distribution panel.
CAUTION !
If the above procedure is not completely performed, it could cause
serious damages to the UPS.
WARNING !
If DC link capacitors not discharged as described in step "4 - discharge DC link
capacitors", the DC link capacitors requires about 15 minutes to discharge
completely.
Wait until capacitors are completely discharged before starting the UPS again.
Apart from the front door, do not open any other part of the UPS.
Modifications reserved
OPM_LPS_3UO_50K_60K_0US_V010.doc
END OF PROCEDURE
COMMAND MENU
INVERTER ON
INVERTER OFF
INVERTER:
U1= 7V
U2= 7V
U3= 7V
Frequency = 60.0Hz
Synchronized
Udcp= 5V
Udcn= 5V
Ubp=0V
Ubn=0V O
Charge level
=
0%
Autonomy
=
0min
MENU COMANDI
INVERTER ON
INVERTER OFF
Operating Manual LP 33 Series 50 & 60 kVA
*
*
Page 50/57

Advertisement

Table of Contents
loading

Table of Contents