II. PRE-START-UP (insert checkmark in box as each item is completed)
VERIFY THAT ALL PACKING MATERIALS HAVE BEEN REMOVED FROM UNIT
REMOVE ALL SHIPPING HOLDDOWN BOLTS AND BRACKETS PER INSTALLATION INSTRUCTIONS
VERIFY THAT CONDENSATE CONNECTION IS INSTALLED PER INSTALLATION INSTRUCTIONS
CHECK ALL ELECTRICAL CONNECTIONS AND TERMINALS FOR TIGHTNESS
CHECK THAT INDOOR-AIR FILTER IS CLEAN AND IN PLACE
VERIFY THAT UNIT INSTALLATION IS LEVEL
CHECK FAN WHEEL AND PROPELLER FOR LOCATION IN HOUSING/ORIFICE AND SETSCREW
TIGHTNESS
III. START-UP
ELECTRICAL
SUPPLY VOLTAGE
INDOOR FAN AMPS
COMPRESSOR AMPS
TEMPERATURES
OUTDOOR-AIR TEMPERATURE
RETURN-AIR TEMPERATURE
HEAT PUMP SUPPLY AIR
ELECTRIC HEATER SUPPLY AIR
PRESSURES
REFRIGERANT SUCTION
REFRIGERANT DISCHARGE
VERIFY REFRIGERANT CHARGE USING CHARGING CHARTS ON PAGES 16 AND 17.
VERIFY SCROLL COMPRESSOR (SIZES 048 AND 060 UNITS) IS ROTATING IN CORRECT DIRECTION.
Copyright 1998 Carrier Corporation
Manufacturer reserves the right to discontinue, or change at any time, specifications or designs without notice and without incurring obligations.
Book 1 4
Catalog No. 015-034
Tab
5a 5a

START-UP CHECKLIST

(Remove and Store in Job File)
L1-L2
L2-L3
L1
Pa
Pa
Printed in U.S.A.
SERIAL NO.:
TECHNICIAN:
L3-L1
L2
DB
DB
WB
PSIG
PSIG
Form 50HS-C5SI
Pg CL-1
L3
5-98
Replaces: 50HS-C3SI

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents