Figure 7 Service clearances for a three rack system (left module)
Table 17 Floor load rating and required clearances for a three rack configuration (left module)
Floor Load
Required Clearance (a+b) m
Rating
Clearance (c) m
(kg/m2)
C=0
500
0.1
450
0.4
400
0.8
350
1.3
C=0.2
C=0.4
0
0
0.2
0.1
0.6
0.4
1.1
0.9
Service clearance, floor cutout, and floor load rating
C=0.6
C=0.6
0
0
0
0
0.3
0
0.7
0.4
29