PREPARATION
SITE PREPARATION
Check the national and local building codes BEFORE installation.
Gate must be constructed and installed according to ASTM F2200 standards (refer
to page 4). Gate must fit specifications of operator (refer to specifications).
GATE
CONDUIT & CONCRETE PAD
Conduit must be UL approved for low and high voltage. Consider the operator
placement BEFORE installing the pad or post.
10
Concrete Pads