30 Storing, lifting and transporting

Lifting instructions

1. To lift the station from the top, install the sling vertically and attach it to the upper corner
castings. See the locations marked in below figure
Top lift spreader configuration
2. To lift the station from bottom, attach the slings from the bottom corner castings to a
spreader bar.
The angle between the slings and the bottom horizontal edge of the station should be
30 degrees and the spreader bar must be a minimum of 500 mm away from the top of
the container. See below figure.

Transporting

WARNING!
Keep the transportation height as low as possible. Make sure the total height of
the transportation is not more than the maximum allowed height.
WARNING!
Transport the MVS on an open heavy-duty chassis. Do not use an enclosed trailer
because the stations surface could easily be damaged.
WARNING!
Do not throw the hooks over the roof. This can damage the paint and cause
corrosion or operation problems.
Obey the following instructions:
Protect the MVS with wooden corners, plastic film, etc. The MVS is delivered unpacked
from the factory as standard.
Protect the interior of the MVS from rainwater by using temporary protection plates
(anti-typhoon) on air intakes and outlets.