Cautions for flare connection
Please refer to the table for the dimensions for processing flares
and for the tightening torques. (Too much tightening will end up
in splitting of the flare.)
Piping
Flare nut
size
tightening torque
32.7~39.9 N•m
Ø9.5
(333~407 kgf•cm)
61.8~75.4 N•m
Ø15.9
(630~770 kgf•cm)
If a torque wrench is not available, be aware that the tightening
torque may increase suddenly. Do not tighten nuts any further
than to the angle as listed.
Piping size
Further tightening angle
Ø9.5
Ø15.9
When connecting the flare nut, apply refrigerating machine oil to
the flare (inside and outside) and first screw the nut 3 or 4 turns
by hand.
Coat here with ether or ester oil.
After completing the installation, carry out a gas leak inspection
of the piping connections with nitrogen and such.
Cautions for necessity of a trap
Since there is fear of the oil held inside the riser piping flowing back into
the compressor when stopped and causing liquid compression
phenomenon, or cases of deterioration of oil return, it will be necessary
to provide a trap at an appropriate place in the riser gas piping.
Trap installation spacing.
A
Outdoor unit
B
Indoor unit
C
Gas piping
D
Liquid piping
E
Oiltrap
H
Install trap at each difference in height of 10 m.
A trap is not necessary when the outdoor unit is installed in a
higher position than the indoor unit.
RZQS71~125B7V3B
Split System air conditioners
4PW32097-1A
4
1
Compressor
2
Terminal cover
4
3
Indoor and outdoor
field piping
4
Corking, etc.
5
5
Insulation material
5
6
Bolts
6
A
Be careful with pipe,
bolt and outer panel
connections
A
A dimensions for
processing flares
(mm)
Flare shape
90° ±2
12.8~13.2
A
19.3~19.7
Recommended arm
length of tool
60°~90°
200 mm
30°~60°
300 mm
(See figure 6)
Cautions for brazing
Be sure to carry out a nitrogen blow when brazing.
Brazing without carrying out nitrogen replacement or releasing
nitrogen into the piping will create large quantities of oxidised
film on the inside of the pipes, adversely affecting valves and
compressors in the refrigerating system and preventing normal
operation. When brazing pipes however, do not use oxidation
preventers. Residue of such preventers may result in choking of
pipes or malfunction of components.
When brazing while inserting nitrogen into the piping, nitrogen
must be set to 0.02 MPa with a pressure-reducing valve (=just
enough so that it can be felt on the skin).
1
1
Refrigerant piping
2
Part to be brazed
3
Taping
4
Hands valve
5
Pressure-reducing valve
6
Nitrogen
E
VACUATING
R=0.4~0.8
Do not purge the air with refrigerants. Use a vacuum pump to
vacuum the installation. No additional refrigerant is provided for
air purging.
Pipes inside the units were checked for leaks by the
manufacturer. The refrigerant pipes fit on site are to be checked
for leaks by the installer.
Confirm that the valves are firmly closed before leak test or
vacuuming.
Set up for vacuuming and leak test:
A
Pair system
B
Simultaneous operation system
1
Pressure gauge
2
Nitrogen
3
Refrigerant
4
Weighing machine
5
Vacuum pump
6
Stop valve
7
Main pipe
8
Branched pipes
9
Pipe branching kit (optional)
2
3
4
6
see
figure 8
5
6
Installation manual
8