7 | Installation

7.4 Mounting paste

7.5 Tightening torques

7.6 Comments on electromagnetic compatibility

54/174
Activity
Removing dust
Damp cleaning, drying
Suction of drilling chips, construction waste, dust
Use mounting paste only according to the installation instructions.
Use only the supplied or released mounting paste.
If not stated otherwise, the following tightening torques apply to the switchgear:
Joint
Metal joints
Earthing busbar
Busbar interconnection
Switchgear earthing
Cable plugs
1)
The tightening torque depends on:
- Material of cable lug
- Information of sealing end manufacturer
- Information of cable manufacturer.
To achieve appropriate electromagnetic compatibility (EMC), some basic requirements must be
observed while erecting the switchgear. This applies especially to the installation and connection
of external cables and wires.
Basic measures for ensuring EMC are already taken during design and assembly of the panels.
Among other things, these measures include:
▪ The low-voltage compartment is an integral part of the panel, which means that the
protection and control devices with the internal wiring are metal-enclosed.
▪ Reliable earth connections of the frame parts via toothed contact washers or locking
washers.
▪ Inside the panel, wires are laid in metal ducts.
▪ Spatial separation of sensitive signal wires from wires with high interference voltage levels.
▪ Limitation of switching overvoltages of inductive loads (e.g. relay or contactor coils, motors)
by means of protective circuits with diode, varistor or RC element.
▪ Within the low-voltage compartment, the secondary devices are mounted in defined zones.
▪ Shortest possible connection between corresponding modules in subracks.
▪ Consideration of the magnetic leakage fields of conductor bars and cables.
▪ Protection of subracks and wiring backplanes against interference by perforated shielding
plates.
▪ Large surface bonding between all modules and devices as well as bonding to the earthing
conductor of the switchgear assembly.
These measures basically enable proper operation of the switchgear itself. The planner or
operator of the switchgear must decide whether additional measures are required depending on
the electromagnetic environment where the switchgear is installed. Such measures must be
implemented by the installation company in charge.
8DJH • Installation and Operating Instructions • Version 11 • 500-8384.9
Cleaning agents
Brush
Lint-free wiping cloths
Vacuum cleaner with plastic tip for sensitive
components
Material/material
Thread
Sheet-steel/sheet-steel
M5
e.g.: front plates, top
M6 (self-tapping)
plates, etc.
M8
Sheet-steel/copper
M8
Copper/copper
M8
Copper/copper
M8
M10
Sheet-steel/cable lug
M12
Cable shield earthing
M10
M16
Tightening torque
7 Nm
12 Nm
30 Nm
20 Nm
20 Nm
20 Nm
40 Nm
1)
50 Nm
1)
30 Nm
1)
max. 50 Nm