Evacuation - LG APUQ55GT3E0 Installation Manual

Floor standing
Table of Contents

Advertisement

LEAKAGE TEST AND EVACUATION
20

Evacuation

- Connect the charge hose end described in
the preceding steps to the vacuum pump to
evacuate the tubing and indoor unit.
Confirm the "Lo and Hi" knob of the manifold
valve is open. Then, run the vacuum pump.
The operation time for evacuation varies with
tubing length and capacity of the pump. The
following table shows the time required for
evacuation.
Required time for evacuation when 4 CFM
vacuum pump is used
If tubing length is
less than 10 m(33 ft)
30 min. or more
0.8 Torr
- When the desired vacuum is reached, close
the "Lo and Hi" knob of the manifold valve
and stop the vacuum pump.
Finishing the Job
- With a service valve wrench, turn the valve
stem of liquid side valve counter-clockwise to
fully open the valve.
- Turn the valve stem of gas side valve counter-
clockwise to fully open the valve.
- Loosen the charge hose connected to the gas
side service port slightly to release the pressure,
then remove the hose.
- Replace the flare nut and its bonnet on the gas
side service port and fasten the flare nut se-
curely with an adjustable wrench. This process
is very important to prevent leakage from the
system.
If tubing length is
longer than 10 m(33 ft)
60 min. or more
- Replace the valve caps at both gas and liquid
side service valves and fasten them tight.
This completes air purging with a vacuum pump.
The air conditioner is now ready to test run.
Indoor unit
Outdoor unit
Manifold valve
Open
Vacuum pump
Pressure
Lo
Hi
gauge
Open

Advertisement

Table of Contents
loading

Table of Contents