7.3.4 To perform vacuum drying

2(A)MXM40+50 + 2(A)MXF40+50
R32 Split series
4P600463-3D – 2021.03
DANGER: RISK OF EXPLOSION
Do NOT start the unit if it is vacuumed.
Connect the vacuum pump and manifold as follows:
a
c
b
d
e
f
g
a Low pressure gauge
b Gauge manifold
c High pressure gauge
d Low-pressure valve (Lo)
e High-pressure valve (Hi)
f Charging hoses
g Vacuum pump
h Valve caps
i Service port
j Gas stop valve
k Liquid stop valve
NOTICE
Connect the vacuum pump to both the service ports of the gas stop valves.
1 Vacuum the system until the pressure on the manifold indicates −0.1  MPa
(−1 bar).
2 Leave as is for 4-5 minutes and check the pressure:
If the pressure...
Does not change
Increases
3 Vacuum the system for at least 2  hours to a manifold pressure of −0.1  MPa
(−1 bar).
4 After turning the pump OFF, check the pressure for at least 1 hour.
5 If you do NOT reach the target vacuum or CANNOT maintain the vacuum for
1 hour, do the following:
▪ Check for leaks again.
▪ Perform vacuum drying again.
NOTICE
Be sure to open the gas stop valve after piping installation and vacuuming. Running
the system with the valve closed, the compressor may break down.
h
k
j
i
h
There is no moisture in the system.
This procedure is finished.
There is moisture in the system. Go
to the next step.
7
Piping installation
|
Then...