Checklist During Commissioning; About Test Run; To Perform A Test Run (7-Leds Display); Correcting After Abnormal Completion Of The Test Run - Daikin RXYSQ6T7Y1B9 Installer's Manual

Vrv iv-s system air conditioner
Hide thumbs Also See for RXYSQ6T7Y1B9:
Table of Contents

Advertisement

Damaged equipment
Check the inside of the unit on damaged components or
squeezed pipes.
Refrigerant leak
Check the inside of the unit on refrigerant leakage. If there
is a refrigerant leak, try to repair the leak. If the repair is
unsuccessful, call your local dealer. Do not touch any
refrigerant which has leaked out from refrigerant piping
connections. This may result in frostbite.
Oil leak
Check the compressor for oil leakage. If there is an oil
leak, try to repair the leak. If the repairing is unsuccessful,
call your local dealer.
Air inlet/outlet
Check that the air inlet and outlet of the unit is not
obstructed by paper sheets, cardboard, or any other
material.
Additional refrigerant charge
The amount of refrigerant to be added to the unit shall be
written on the included "Added refrigerant" plate and
attached to the rear side of the front cover.
Installation date and field setting
Be sure to keep record of the installation date on the
sticker on the rear of the front panel according to
EN60335‑2‑40 and keep record of the contents of the field
setting(s).
8.4

Checklist during commissioning

To perform a test run.
8.4.1

About test run

The procedure below describes the test operation of the complete
system. This operation checks and judges following items:
▪ Check of wrong wiring (communication check with indoor units).
▪ Check of the stop valves opening.
▪ Judgement of piping length.
Make sure to carry out the system test operation after the first
installation. Otherwise, the malfunction code
the user interface and normal operation or individual indoor unit test
run cannot be carried out.
Abnormalities on indoor units cannot be checked for each unit
separately. After the test operation is finished, check the indoor units
one by one by performing a normal operation using the user
interface. Refer to the indoor unit installation manual for more details
concerning the individual test run.
INFORMATION
▪ It may take 10 minutes to achieve a uniform refrigerant
state before the compressor starts.
▪ During the test operation, the refrigerant running sound
or the magnetic sound of a solenoid valve may become
loud and the display indication may change. These are
not malfunctions.
8.4.2

To perform a test run (7-LEDs display)

1 Make sure all field settings you want are set; see
field settings" on
page 27.
2 Turn ON the power to the outdoor unit and the connected
indoor units.
RXYSQ6T7Y1B9
VRV IV-S system air conditioner
4P404677-1A – 2016.03
3 Make sure the default (idle) situation is existing (H1P is OFF);
see
seconds or more. The unit will start test operation.
Result: The test operation is automatically carried out, the
outdoor unit H2P flashes and the indication "Test operation"
and "Under centralised control" will display on the user interface
of indoor units.
Steps during the automatic system test run procedure:
4 Check the test operation results on the outdoor unit 7‑LEDs
display.
Normal
completion
Abnormal
completion
will be displayed on
8.4.3
The test operation is only completed if there is no malfunction code
displayed. In case of a displayed malfunction code, perform
correcting actions as explained in the malfunction code table. Carry
out the test operation again and confirm that the abnormality is
properly corrected.
8.4.4
Once the unit is installed and test operation of outdoor unit and
"7.2  Making
indoor units is finished, the operation of the system can start.
For operating the indoor unit, the user interface of the indoor unit
should be switched ON. Refer to the indoor unit operation manual for
more details.
NOTICE
Be sure to turn on the power 6 hours before operation in
order to have power running to the crankcase heater and
to protect the compressor.
"7.2.4 To access mode 1 or 2" on
Step
Control before start up (pressure
equalisation)
Cooling start up control
Cooling stable condition
Communication check
Stop valve check
Pipe length check
Pump down operation
Unit stop
INFORMATION
During the test operation, it is not possible to stop the unit
operation from a user interface. To abort the operation,
press BS3. The unit will stop after ±30 seconds.
Completion
Refer to
"8.4.3 Correcting after abnormal
completion of the test run" on page 35
actions for correcting the abnormality. When
the test operation is fully completed, normal
operation will be possible after 5 minutes.
Correcting after abnormal completion of
the test run
INFORMATION
If a malfunction occurs, the error code is displayed on the
user interface of the indoor unit.
INFORMATION
Refer to the installation manual of the indoor unit for other
detailed malfunction codes related to indoor units.

Operating the unit

8 Commissioning
page 28. Push BS4 for 5
Description
Description
to take
Installer and user reference guide
35