Commissioning

NOTICE
General
commissioning
commissioning instructions in this chapter, a general
commissioning checklist is also available on the Daikin
Business Portal (authentication required).
The general commissioning checklist is complementary to
the instructions in this chapter and can be used as a
guideline and reporting template during commissioning and
hand-over to the user.
NOTICE
ALWAYS operate the unit with thermistors and/or pressure
sensors/switches. If NOT, burning of the compressor might
be the result.
NOTICE
For models with integrated backup heater: The unit
contains an automatic air purge valve on the backup
heater. Make sure it is open. All automatic air purge valves
in the system (in the unit, and in the field piping –if any)
must remain open after commissioning.
For other models: The unit contains a manual air purge
valve. Make sure it is closed. Only open it when performing
an air purge.
INFORMATION
Protective functions – "Installer-on-site mode". The
software is equipped with protective functions, such as
room antifrost. The unit automatically runs these functions
when necessary.
During installation or service this behaviour is undesired.
Therefore, the protective functions can be disabled:
▪ At first power-on: The protective functions are
disabled by default. After 12 hours they will be
automatically enabled.
▪ Afterwards: An installer can manually disable the
protective
functions
protections=Yes. After his work is done, he can
enable the protective functions by setting [9.G]:
Disable protections=No.
9.1

Checklist before commissioning

1 After the installation of the unit, check the items listed below.
2 Close the unit.
3 Power up the unit.
You read the complete installation instructions, as
described in the installer reference guide.
The outdoor unit is properly mounted.
Field wiring
Be sure that the field wiring has been carried out
according to the instructions described in the chapter
"6  Electrical
installation"  [ 4   21], according to the wiring
diagrams and according to the applicable legislation.
EBLA09~16D + EDLA09~16D
Daikin Altherma 3 M
4P620239-1B – 2022.05
checklist.
Next
to
the
by
setting
[9.G]:
Disable
The system is properly earthed and the earth terminals
are tightened.
The fuses or locally installed protection devices are
installed according to this document, and have NOT been
bypassed.
The power supply voltage matches the voltage on the
identification label of the unit.
There are NO loose connections or damaged electrical
components in the switch box.
There are NO damaged components or squeezed
pipes on the inside of the outdoor unit.
Only for models with integrated backup heater (F1B: field
supply), or if the external backup heater kit (F1B: factory-
mounted in the backup heater kit) is installed:
Backup heater circuit breaker F1B is turned ON.
Only for tanks with built-in booster heater:
Booster heater circuit breaker F2B (field supply) is
turned ON.
The correct pipe size is installed and the pipes are
properly insulated.
There are no water leaks inside the outdoor unit.
The shut-off valves are properly installed and fully open.
For models with integrated backup heater: The automatic
air purge valve (on the backup heater) is open.
For other models: The manual air purge valve is closed.
The pressure relief valve (space heating circuit) purges
water when opened. Clean water MUST come out.
The minimum water volume is guaranteed in all
conditions. See "To check the water volume and flow rate"
in
"5.1 Preparing water
(if applicable) The domestic hot water tank is filled
completely.
9.2

Checklist during commissioning

The minimum flow rate is guaranteed in all conditions.
See "To check the water volume and flow rate" in
piping" [ 4  17].
"5.1 Preparing water
To perform an air purge.
To perform a test run.
To perform an actuator test run.
Underfloor screed dryout function
The underfloor screed dryout function is started (if
necessary).
9.2.1

To check the minimum flow rate

1 Check the hydraulic configuration to find out which
space heating loops can be closed by mechanical,
electronic, or other valves.
2 Close all space heating loops that can be closed.
3 Start the pump test run (see
run" [ 4  46]).
actuator test
(a)
4 Read out the flow rate
and modify the bypass valve
setting to reach the minimum required flow rate + 2 l/
min.
(a)
During pump test run, the unit can operate below the minimum
required flow rate.
9 Commissioning