4.3

Dismantling

For dismantling the load cells, the same safety rules apply as for installation.
1. Disconnect all the supply voltages and auxiliary voltages.
2. Secure the load carrier against falling.
3. Use appropriate hoisting gear and tools.
4. Take the load off the load cell.
5. Carefully remove the load cell without using force. Do not pull on the cable of the load cell.
6. If you intend to reinstall the load cell or send it for repair, do not cut the load cell cable.
7. Do not carry the load cell by the cable.
SIWAREX WL200
Operating Instructions, 12/2021, A5E02199611B-13
Installing
4.3 Dismantling
23

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Siwarex wl250 seriesSiwarex wl230 seriesSiwarex wl270 seriesSiwarex wl280 seriesSiwarex wl290 seriesSiwarex wl260 sp-s aa ... Show all

Table of Contents