6.3 Assembly work

For assembly work to be carried out, the following prerequisites must be fulfilled and the preparatory tasks must have 
been completed.
Tools
Spanner or adjustable end wrench
Depressurise the pressurised system or the respective system section and secure it against unintentional
1.
pressurisation.
2.
Get the hose and hose clamp ready for connection to the condensate discharge.
Illustration
36
F
Right
Prerequisites
Material
Sealants e.g. PTFE
Feed line
Drain line
Hose, interior diameter
8 ... 10 mm (0.31 ... 0.39 in),
length approx. 30 cm (1 ft)
Hose clamp
Preparatory tasks
Assembly work
Description / explanation
25
1. Remove the plugs [25, 36] on the inlet connection [F]
and drain connection [D].
D
BEKOMAT
14i / 14i CO / 14i CO PN25
®
Description / explanation
Discharge from pressurised pipes
Divert the flow of gas to provide a deflecting 
surface to discharge the fluid components in 
the gas.
Protective equipment
Always to be worn:
37 | 76

Advertisement

Table of Contents
loading

This manual is also suitable for:

Bekomat 14i coBekomat 14i co pn25

Table of Contents