Step 7 Connecting The Assembly Pipes To The Refrigerant Pipes - Samsung AJ RB1DEG Series Installation Manual

Hide thumbs Also See for AJ RB1DEG Series:
Table of Contents

Advertisement

Installation Procedure
Step 7 Connecting the assembly pipes
to the refrigerant pipes
There are two refrigerant pipes of different diameters :
• A smaller one for the liquid refrigerant.
• A larger one for the gas refrigerant. The inside of
copper pipe must be clean and has no dust.
1 Remove the pinch pipe on the pipes and connect the
assembly pipes to each pipe, tightening the nuts, first
manually and then with a torque wrench, a spanner
applying the following torque.
1
Spanner
3
Union
Outer Diameter (mm)
Ø6.35
Ø9.52
Ø12.70
Ø15.88
(1 N
m = 10 kgf cm)
10
English
2
Torque
wrench
3
Flare nut
14 to 18
34 to 42
49 to 61
68 to 82
NOTE
• If the pipes must be shortened, see Step 6 Cutting
and flaring the pipes on page 9.
2 Be sure to use an insulator thick enough to cover the
refrigerant tube to protect the condensate water on
the outside of the pipe falling onto the floor and to
improve the efficiency of the unit.
3 Cut off any excess foam insulation.
4 Make sure that there are no cracks or waves on the
bent area.
5 It would be necessary to double the insulation
thickness (10 mm or more) to prevent condensation
even on the insulator when if the installed area is
warm and humid.
6 Do not use joints or extensions for the pipes
connecting the indoor and outdoor units. The only
permitted connections are those for which the units
are designed.
CAUTION
• Connect the indoor and outdoor units using pipes
with flared connections (not supplied). For the lines,
use insulated, unwelded, degreased and deoxidized
copper pipe (Cu DHP type to ISO 1337 or UNI EN 12735-
1), suitable for operating pressures of at least 4.2 MPa
and for a burst pressure of at least 20.7 MPa. Copper
pipe for hydro-sanitary applications is completely
unsuitable.
• For sizing and limits (height difference, line length,
max. bends, refrigerant charge, etc.) see the outdoor
unit installation manual.
• All refrigerant connection must be accessible, in order
to permit either unit maintenance or removing it
completely.
• If the pipes require brazing, make sure that oxygen
free nitrogen (OFN) is flowing through the system.
• Nitrogen blowing pressure range is 0.02 to 0.05 MPa.

Advertisement

Table of Contents
loading

This manual is also suitable for:

Aj035rb1deg/eu

Table of Contents