GAS SUPPLY AND PIPING

The gas piping system must meet the requirements of local
codes or the specifications of the servicing gas supplier. It
must have adequate capacity to supply the floor furnace
and any other appliance within the home with enough
gas to maintain the full rated capacities without excessive
pressure drop when all appliances are operating at full rate.
GAS PIPE SIZES - CAPACITY NATURAL GAS *
INSIDE PIPE DIAMETER
LENGTH OF
PIPE - FEET
1/2"
10
132,000
20
92,000
30
73,000
40
63,000
50
56,000
60
50,000
*
Based on heating value of 1,000 value of 1,000 BTU per cubic
foot(specif ic gravity of 0.6) at 0.5 PSIG and a pressure drop of
0.3 inch water column.
GAS TUBING AND PIPE SIZES - CAPACITY PROPANE GAS *
COPPER TUBING
LENGTH
OUTSIDE DIAMETER**
OF PIPE
FEET
1/2"
3/4"
10
92,000
329,000
20
62,000
216,000
30
50,000
181,000
40
41,000
145,000
50
37,000
131,000
60
35,000
121,000
* Undiluted Liquefied Petroleum Gas at 11 inches water column inlet
pressure. Based on a pressure drop of 0.5 inches water column.
** Copper tubing must comply with limitations of NATIONAL FUEL GAS
CODE reference 2.6.3 metallic tubing.
*** Steel pipe should be of at least standard weight (Schedule 40).
Support the piping or tubing at regular intervals with
metal pipe strapping. See charts below.
NOMINAL STEEL PIPE SIZE
1/2"
3/4" or 1"
NOMINAL SIZE OF TUBING O.D.
1/2"
5/8" or 3/4"
3/4"
1"
278,000
520,000
190,000
350,000
CAPACITY
152,000
285,000
BTU/hr
130,000
245,000
115,000
215,000
105,000
195,000
STEEL PIPE
INSIDE DIAMETER***
1/2"
3/4"
275,000
567,000
189,000
393,000
CAPACITY
152,000
315,000
129,000
267,000
114,000
237,000
103,000
217,000
SPACING OF SUPPORTS
6'
8'
SPACING OF SUPPORTS
4'
6'
• Where local conditions include earthquake, tornado,
unstable ground or flood hazards, give special
consideration to increased strength and flexibility
of piping supports and connections. Consult local
authorities for recommendations.
• All unused openings in the piping system must be
securely closed gas-tight.
Refer to Figure 10 for the basic fittings you will need
at the furnace.
1. Use black iron or steel pipe and fittings or other pipe
and fittings that are approved by local codes.
2. Use pipe joint compound that is resistant to the action
of Propane Gas or to any other chemical constituents of
the gases to be conducted through the piping only on
male threads.
3. Use two wrenches when making the connection to the
INPUT
valve to keep from bending the mounting bracket or
manifold pipe. Do not over tighten as damage to the
valve can occur.
4. Provide a 1/8" nominal pipe thread (NPT) plugged
tapping for test gauge connection immediately
upstream of the gas supply connection to the floor
furnace.
5. Provide a sediment trap at least 6 inches long to trap
dirt and moisture. Provide space to permit cleaning
or emptying.
6. Use a ground joint union.
7. Install an approved manual shut-off valve.
BTU/hr
INPUT
TO HEATER GAS
CONTROL VALVE
MANUAL CUT-OFF VALVE
1/8" NPT
PRESSURE TAP
DRIP LEG
GAS FIRED VENTED FLOOR FURNACES
GAS
SUPPLY
LINE
11

Hide quick links:

Advertisement

Chapters

Table of Contents
loading

This manual is also suitable for:

90n50a90n65a

Table of Contents