Gas Supply And Piping - COZY 90N30A Installation And Operating Instructions Manual

Gas-fired vented floor furnace
Table of Contents

Advertisement

CONNECTING THE VENT - Continued
Typical Installation Using
Class "B" Vent Pipe
1. Adequate clearances around floor furnace.
2. Draft Diverter 6" from combustibles.
3. Adequate clearances around vent pipe.
4. Horizontal vent pipe sloping upward 1/4" per foot.
5. Pipe supported with metal straps.
6. Adequate height of vent system.
7. Listed vent cap.
FIGURE 10
The gas piping system must meet the requirements of local codes or the specifications of the servicing gas supplier. It must
have adequate capacity to supply the floor furnace and any other appliance within the home with enough gas to maintain the
full rated capacities without excessive pressure drop when all appliances are operating at full rate.
GAS PIPE SIZES - CAPACITY - *NATURAL GAS
Length of
INSIDE PIPE DIAMETER
Pipe - Feet
1/2"
1 0
132,000 278,000 520,000
2 0
92,000 190,000 350,000
3 0
73,000 152,000 285,000
4 0
63,000 130,000 245,000
5 0
56,000 115,000 215,000
6 0
50,000 105,000 195,000
*Based on heating value of 1,000 btu per cubic foot (specific gravity
of 0.6) @ 0.5 PSIG and a pressure drop of 0.3 inch water column.
Support the piping or tubing at regular intervals with
metal pipe strapping. See chart below.
Nominal Steel
Pipe Size
1/2"
3/4" or 1"
Where local conditions include earthquake, tornado, unstable ground or flood hazards, give special consideration to
increased strength and flexibility of piping supports and connections. Consult local authorities for recommendations.
All unused openings in the piping system must be securely closed gas-tight.

GAS SUPPLY AND PIPING

3/4"
1"
Capacity
B.T.U.
Per Hour
Input
Spacing of
Supports
6'
8'
If more than one gas appliance is vented through
a common vent system, the vent should be
increased in size to accommodate the increased
load. Consult your local code or the tables in the
latest edition of NFPA54/ANSI.Z223.1 for the
correct size. If no local codes apply, use the
following alternate method for sizing a vent
connected to more than one appliance. The
effective area of the vent must be not less than
the area of the largest vent connection plus 50
percent of the areas of additional draft hood
outlets.
The homeowner appreciates neatness in
workmanship and the neat installation usually
functions better than the sloppy one. Double
check your work to verify that all clearances around
the floor furnace and vent system are adequate
and that the vent system is installed to code or
pipe manufacturers specifications. See Figure 10.
GAS TUBING AND PIPE SIZES - CAPACITY -
Length of
**Copper Tubing
Pipe/Tubing
Outside Diameter
Feet
1/2"
1 0
92,000
2 0
62,000
3 0
50,000
4 0
41,000
5 0
37,000
6 0
35,000
*Undiluted Liquefied Petroleum Gas @ 11 inches water column inlet
pressure. Based on a pressure drop of 0.5 inches water column.
**Copper tubing must comply with limitations of NATIONAL FUEL
GAS CODE reference 2.6.3 metallic tubing.
***Steel pipe should be of at least standard weight (Schedule 40).
Nominal size of
tubing O.D.
1/2"
5/8" or 3/4"
Page 8
*L.P. GAS
**Steel Pipe
Inside Diameter
3/4"
1/2"
3/4"
329,000 275,000 567,000
216,000 189,000 393,000
181,000 152,000 315,000
145,000 129,000 267,000
131,000 114,000 237,000
121,000 103,000 217,000
Spacing of
Supports
4'
6'
Capacity
B.T.U.
Per Hour
Input

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

90n50a90n65a90n75a

Table of Contents