DC breaker switch

Replacing the DC breaker switch

Tools:
• Wrenches, socket set, screw drivers etc. standard installation tools. Recommendation:
A 24 mm and a 34 mm open-jaw crowfoot wrench and an extension bar for opening and
removing of the cooling pipe connectors below the module.
• A torque wrench
• New gasket for the pipe connector. Recommendation: REINZ-AFM-34 flat gasket.
• A lift or a hoist for removing and replacing the DC breaker switch, including lifting beam(s)
and slings if needed. Make sure that you can attach the hoist to all four lifting eyes and
align the lifting slings as vertical as possible. The DC breaker switch is heavy. Depending
on the size, it weighs 65 to 145 kg.
• Lifting eyes for the DC breaker switch (loose objects inside the cabinet).
• Heat gun for warming up pipe ends for easier removal.
• An empty pallet for removing the old DC breaker switch out of the site.
WARNING!
Obey the safety instructions of the drive. If you ignore them, injury or death,
or damage to the equipment can occur. If you are not a qualified electrical
professional, do not do installation or maintenance work.
WARNING!
Beware of hot coolant. Do not work on the liquid cooling system until the pressure
is lowered down by stopping the pumps and draining the coolant. High-pressure
warm coolant (6 bar, max. 50 °C) is present in the internal cooling circuit when it
is in operation.
WARNING!
Use the required personal protective equipment. Wear protective gloves and long
sleeves. Some parts have sharp edges.
WARNING!
Be very careful when you remove bolts and screws. Do not drop anything inside
the cabinet. It can cause severe damage at the power up: short circuit or arc blast.