2.5.4 Openings

2.6 Inspections, records

14 - Transport and Unpacking
If there are any openings where cables are not connected to terminal boxes or flanges that are
not connected to the piping, they are to be sealed. The coolers and the piping within the machine
are to be cleaned and dried before they are sealed. The drying is made by blowing warm and dry
air through the pipes.
The storage period, taken precautions and measurements, including dates, should be recorded.
For relevant check-lists, see Appendix COMMISSIONING REPORT.