Unit Start-Up - Lennox Dave Signature SL28XCV Installation Instructions Manual

Table of Contents

Advertisement

UNIT START-UP

IMPORTANT
If unit is equipped with a crankcase heater, it should
be energized 24 hours before unit start-up to prevent
compressor damage as a result of slugging.
1 - Rotate fan to check for binding.
2 - Inspect all factory- and field-installed wiring for
loose connections.
3 - After evacuation is complete, open the liquid line and
vapor line service valve stems to release the refrigerant
charge (contained in outdoor unit) into the system.
4 - Replace the stem caps and tighten to the value
listed in table 2.
5 - Check voltage supply at the disconnect switch. The
voltage must be within the range listed on the unit's
nameplate. If not, do not start the equipment until
you have consulted with the power company and
the voltage condition has been corrected.
6 - Connect manifold gauge set for testing and charging
or use the Lennox Dealer Setup App to monitor the
pressures and temperatures of the refrigeration
system.
7 - Turn on power to the indoor unit and close the
outdoor unit disconnect switch to start the unit.
Start-up and testing should be performed with the
unit operating at the maximum cooling capacity
(100% capacity). The unit can be operated at
maximum capacity by entering the test mode at
the thermostat or using the Lennox Dealer Setup
App. The S30 Test Mode can be selected by going
to Menu> Advanced Settings> View Dealer Control
Center> Test and then select Cooling - Maximum
Rate Test.
8 - Recheck voltage while the unit is running. Power
must be within range shown on the unit nameplate.
9 - Check system for sufficient refrigerant using the
procedures outlined under Checking Refrigerant
Charge.
OPERATING MANIFOLD GAUGE SET AND SERVICE
VALVES
The liquid and vapor line service valves are used for re-
moving refrigerant, flushing, leak testing, evacuating,
checking charge and charging.
Each valve is equipped with a service port which has a
factory-installed valve stem. Figures 14 and 15 provide
information on how to access and operate both angle- and
ball-type service valves.
Torque Requirements
When servicing or repairing heating, ventilating and air
conditioning components, ensure the fasteners are appro-
priately tightened. Table 2 lists torque values for fasteners.
TABLE 1
Parts
Service valve cap
Sheet-metal screws
Machine screws #10
Compressor bolts
Gauge port seal cap
To prevent stripping of the various caps used, the
appropriately sized wrench should be used and fitted
snugly over the cap before tightening.
Using Manifold Gauge Set
When checking the system charge, only use a manifold
gauge set that features low loss anti-blow back fittings.
Manifold gauge set used with HFC-410A refrigerant sys-
tems must be capable of handling the higher system oper-
ating pressures. The gauges should be rated for use with
pressures of 0 - 800 psig on the high side and a low side
of 30" vacuum to 250 psig with dampened speed to 500
psi. Gauge hoses must be rated for use at up to 800 psig
of pressure with a 4000 psig burst rating.
OPERATING BALL-TYPE SERVICE VALVE
1 - Remove stem cap with an appropriately sized wrench.
2 - Use an appropriately sized wrench to open. To open valve, rotate
stem counterclockwise 90°. To close, rotate stem clockwise 90°.
TO OPEN, ROTATE STEM
COUNTERCLOCKWISE 90°.
TO CLOSE, ROTATE STEM
CLOCKWISE 90°.
SERVICE PORT
SERVICE PORT
SERVICE PORT
Page 19
– TORQUE REQUIREMENTS
Recommended Torque
8 ft.-lb.
11 NM
16 in.-lb.
2 NM
28 in.-lb.
3 NM
90 in.-lb.
10 NM
8 ft.-lb.
11 NM
IMPORTANT
BALL (SHOWN
CLOSED)
CORE
CAP
FIGURE 13
VALVE
STEM
STEM CAP

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents