Contents 7820A GC Site Preparation Customer Responsibilities Site Preparation Good Practices Agilent Technologies Installation and Familiarization Services Computer Requirements Dimensions and Weight Power Consumption Grounding Heat Dissipation Exhaust Venting Environmental Conditions Gas Selection Gas Supply Gas Plumbing Supply tubing for carrier and detector gases...
Agilent 7820A GC Site Preparation Guide 7820A GC Site Preparation Customer Responsibilities Computer Requirements Dimensions and Weight Power Consumption Heat Dissipation Exhaust Venting Environmental Conditions Gas Selection Gas Supply Gas Plumbing Maximum Length of Cables Site LAN Network Basic Tools and Consumables This section outlines the space and resource requirements for GC and automatic liquid sampler (ALS) installation.
In extreme cases, Agilent Technologies may ask to be reimbursed for the additional time required to complete the installation. Agilent Technologies provides service during the warranty period and under maintenance agreements only if the specified site requirements are met.
7820A GC Site Preparation Agilent Technologies Installation and Familiarization Services If you purchased installation and familiarization services from Agilent, these services include: • Installation of the GC • Installation of purchased Agilent software • Agilent chemical test to verify GC function •...
7820A GC Site Preparation Computer Requirements A computer is required for 7820A GC installation and operation. The computer must meet the minimum requirements to run the Agilent Instrument Utility. Table 1 lists these requirements for version B.01.01 of the Instrument Utility.
Computer with monitor Printer Figure 1 Top view of typical installation (7820A GC system) A simple 7820A system that includes a GC, ALS injector, and a computer would require about 111 cm (3 ft 8 in.) of bench space. Allowing for operational access and a printer, a total of 153 cm (5 ft) of bench space should be available for a full GC system.
Although your GC should arrive ready for operation in your country, compare its voltage requirements with those listed in Table 3. If the voltage option you ordered is not suitable for your installation, contact Agilent Technologies. 7820A GC Site Preparation Guide...
A properly grounded receptacle is one that is connected to a suitable earth ground. Be sure to verify proper receptacle grounding. Connect the GC to a dedicated receptacle. Use of a dedicated receptacle reduces interference. 7820A GC Site Preparation Guide...
Maximums represent the heat given off when heated zones are set for maximum temperatures. Table 4 Heat dissipation Oven type Standard oven ramp 100 V Power option Agilent 7820A 7681 BTU/hour maximum 5120 BTU/hour maximum 7820A GC Site Preparation Guide...
Place the GC in the hood or attach a large diameter venting tube to the outlet for proper ventilation. To further prevent contamination from noxious gases, attach a chemical trap to the vent(s). 7820A GC Site Preparation Guide...
Environmental conditions for operation and storage Product Conditions Operating temp Operating Maximum range humidity range altitude Agilent 7820A Standard oven ramp 5 to 45 °C 5 to 90% 3,100 m Storage –20 to 65 °C 0 to 90% 7820A GC Site Preparation Guide...
Maximum sensitivity Nitrogen Argon/methane Maximum dynamic range Argon/Methane Flame ionization (FID) Nitrogen Maximum sensitivity Hydrogen and air for detector. Helium Acceptable alternative Nitrogen-Phosphorus (NPD) Helium Optimum performance Hydrogen and air for detector. Nitrogen Acceptable alternative 7820A GC Site Preparation Guide...
Page 16
Gases required for checkout Detector Gases required Carrier: helium Makeup: nitrogen Fuel: hydrogen Aux gas: Air Carrier and reference: helium Carrier: helium Makeup: nitrogen Fuel: hydrogen Aux gas: Air uECD Carrier: helium Anode purge and makeup: nitrogen 7820A GC Site Preparation Guide...
Table 10 Delivery pressures required at the GC, in kPa (psig) Detector type Inlet type uECD Split/Splitless Purged packed Hydrogen 240–690 240–690 (35–100) (35–100) 380–690 380–690 (55–100) (55–100) Makeup 380–690 380–690 380–690 380–690 (55–100) (55–100) (55–100) (55–100) Reference 380–690 (55–100) 7820A GC Site Preparation Guide...
Page 18
(55 psig). This air supply must end in a male fitting compatible with a 1/4-inch id plastic tube at the GC. • Never use liquid thread sealer to connect fittings. Never use chlorinated solvents to clean tubing or fittings. 7820A GC Site Preparation Guide...
High-quality, stainless-steel diaphragm-type regulators are especially recommended. • On/off valves mounted on the outlet fitting of the two-stage regulator are not essential but are very useful. Be sure the valves have stainless-steel, packless diaphragms. 7820A GC Site Preparation Guide...
Be generous when cutting tubing for local supply lines—a coil of flexible tubing between the supply and the instrument lets you move the GC without moving the gas supply. Take this extra length into account when choosing the tubing diameter. 7820A GC Site Preparation Guide...
The Agilent catalog for consumables and supplies contains information to help you identify the correct regulator, as determined by the Compressed Gas Association (CGA). Agilent Technologies offers pressure-regulator kits that contain all the materials needed to install regulators properly. Pressure regulator-gas supply tubing connections ®...
Place it last in a series of traps. Because trace amounts of oxygen can damage columns and degrade uECD performance, use an oxygen trap with carrier and uECD gases. Do not use it with FID or NPD fuel gases. 7820A GC Site Preparation Guide...
• The length of the Agilent-supplied remote cable is 2 meters (6.6 feet). • The length of the Agilent-supplied LAN cable is 10 meters (32.8 feet). • The lengths of the power cords are 2 meters (6.6 feet). 7820A GC Site Preparation Guide...
If you intend to connect your system to your site’s LAN network, you must have an additional shielded twisted pair network cable. Agilent Technologies is not responsible for connecting to or establishing N O T E communication with your site LAN network. The representative will test the system’s ability to communicate on a mini-hub or LAN switch only.
Digital flow meter, Flow tracker 1000 Verifying flows, checking for leaks and plugs Electronic gas leak detector Locating gas leaks; safety checks when using Hydrogen Electronic vial crimper Assuring consistently air-tight vial closure, regardless of who does the crimping 7820A GC Site Preparation Guide...
Page 26
Kits with individual parts needed to kits maintain an inlet Pneumatic supplies Gases, traps, o-rings, seals, Swagelok fittings Column supplies Nuts, ferrules, adapters, guard columns, retention gaps Detector supplies Jets, beads, liners, adapters, cleaning kits Application supplies Standards, columns, syringes 7820A GC Site Preparation Guide...
Agilent 7820A GC Site Preparation Guide 7693A Automatic Liquid Sampler Site Preparation Customer Responsibilities Dimensions and Weight Power Consumption Environmental Conditions Basic Tools This section outlines the space and resource requirements for a 7693A automatic liquid sampler (ALS). For a successful and timely installation of the ALS, the site must meet these requirements before beginning installation.
In extreme cases, Agilent Technologies may ask to be reimbursed for the additional time required to complete the installation. Agilent Technologies provides service during the warranty period and under maintenance agreements only if the specified site requirements are met.
Table 2 Environmental conditions for operation and storage Product Conditions Operating temp Operating humidity range Maximum range altitude G4513A Injector, Operation –5 to 45 °C 5–95% 4,300 m G4514A Tray, G4515A Bar Code Reader 7820A GC Site Preparation Guide...
Below is a general list of what comes with the instrument. Table 3 Basic tools and consumables Tool or consumable Used for T10 Torx wrench Replacing turret. Replacing syringe carriage. Sample vial starter pack Syringe, 10 uL 7820A GC Site Preparation Guide...
Agilent 7820A GC Site Preparation Guide Site Preparation Readiness Before Contacting Agilent for Installation This appendix contains an important form that Agilent requires as a prerequisite to Agilent installation and familiarization services. Agilent Technologies...
Bangalore : +91-80-41665120 Gurgoan : +91-124-4727102 Mumbai : +91-22-30648339 China +86 8008201182 yanzl@neower.com Arrange the installation date. After arranging an installation date, you must still make sure that the appropriate personnel will be available during the installation. 7820A GC Site Preparation Guide...
Page 33
Site Readiness Certification I have read and understand the 7820A GC Site Preparation requirements, and certify that the site has been prepared for instrument installation as described in this manual, including: ❑ Adequate space and suitable supporting bench available ❑...