Installation Checklist - Trane RTRA Series Installation Operation & Maintenance

Screw compressor liquid chillers with centrifugal fans, air cooled, sizes : 107 - 108 - 109 - 110
Table of Contents

Advertisement

Installation checklist

RTRA Trane Air Cooled Liquid Chiller
This list must be checked off by the installer to ensure correct installation before the unit starts up.
Unit acceptance
Check for damage, if any, on transportation
Check for equipment shipped against delivery slip
Check lifting system
Unit positioning
Remove packaging
Check position of unit
Check unit is level
Check clearance around condenser
Check clearance required for maintenance access
Check position of rubber pads
Chilled water circuit
Check presence of strainer ahead of evaporator
Check the tightness of the water circuit
Check thermometer positioning
Check manometer positioning
Check chilled water flow rate balancing system
Check rinsing and filling of chilled water pipes
Check pump operation and water flow
Electrical equipment
Check direction of rotation of compressors and fan motors
Check installation and rating of mains power switch/fuse
Check that electrical connections comply with specification
Check that electrical connections match information on manufacturer's identification plate
Check electrical connections and connections to mains power switch
Water pressure switch
Ducting
External pressures of air inlet and discharge ducting
General
Check available cooling charge (50% of rated installation load)
Check with other trades handling installation works
Comments : ...........................................................................................................................................................................
................................................................................................................................................................................................
................................................................................................................................................................................................
................................................................................................................................................................................................
................................................................................................................................................................................................
Signature : ...........................................................
Order N° ...............................................................................................................................................................................
Work site : ............................................................................................................................................................................
Please return to your local Trane Service Agency