2.
Using the hole drilled in step 1, insert eight inches of 1/4
inch metal tubing into the airflow of the return and supply
air ducts of the unit.
Note: You must insert the tubes and hold them in a position
perpendicular to the air flow so that velocity pressure
does not affect the static pressure readings.
3.
Use an inclined manometer or Magnehelic® to determine
the pressure drop across the unit. This is the external static
pressure (ESP). In order to obtain an accurate
measurement, verify that the air filters are clean.
4.
Determine the number of turns the variable motor sheave
is open.
5.
Select the correct blower performance table for the unit
from Table 18. Tables are presented for side and bottom
duct configuration.
6.
Determine the unit measured CFM from the blower
performance table, external static pressure, and the
number of turns the variable motor sheave is open.
0.7
0.65
0.6
0.55
0.5
0.45
0.4
0.35
0.3
0.25
0.2
0.15
0.1
0.05
0
1500
Figure 30: Dry coil delta P
Johnson Controls Ducted Systems
2000
2500
3000
100% Return Economizer
7.
To adjust measured CFM to required CFM, see Supply air
drive adjustment on page 48.
8.
After you note the reading, remove the tubes and seal the
holes.
9.
Tighten the blower pulley and motor sheave set screws
after any adjustments. Re-check the set screws after 10-12
hours run time.
Note: You must repeat this procedure with the addition of
field-installed accessories.
Failure to properly adjust the total system air quantity
can result in extensive blower damage.
ZR078
ZR090
3500
4000
4500
Air Flow Rate (cfm)
No Economizer
5167531-YIM-J-1019
ZR102
ZR120
ZR150
5000
5500
6000
6500
47

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Zr078Zr090Zr102Zr120Zr150

Table of Contents