Wall Mount Installation; Cabinet Installation - Thermador HPWB30 Installation Manual

Thermador ventilation hood installation manual
Hide thumbs Also See for HPWB30:
Table of Contents

Advertisement

Available languages

Available languages

Wall Mount Installation

Note: see below if cabinet installation is preferred
3. After the hood installation height has been
determined draw a horizontal line at a distance
above the cooktop equal to the desired hood
installation height plus 7- 1/2". See also Figure 4a.
4. Find the centerline of the cooktop. Draw a
vertical line along this centerline up to the hori-
zontal line drawn in step 1 and draw a vertical
line right and left at a distance of12-5/8" to
determine the mounting locationof the
mounting hooks shipped with the hood.
5. Fit two mounting hooks on the wall to hang the
hood through the provided slots (2 wall
anchors + 2 hooks + 2 screws 5x35).
6. Run 10" Duct, long enough to reach the
transition once the hood has been installed plus
1 1/2" inch to connect ductwork. Fix Duct to
transition with screws and seal withtape.
7. Remove 1 of 2 knockouts and install 1/2"
conduit connector in j-box.
8. Hang the hood and adjust its position through
the screws on the hooks.
9. Fix the hood to 4 additional point, 2 on
upperside, 2 on lower side (use 4 wall anchors
+ 4washers + 4 screws 5x35.

Cabinet Installation:

Note: See above if wall mount installation is preferred
Note: Distances on Table 3.3
Find the centerline of the cabinet bottom. Draw a line
along this centerline from rear to front of the cabinet.
See also Figure 4b.
4. Draw two lines, one at a K distance from thewall,
the other one at a Z distance from theprevious line.
Mark 4 points, two along each line at a distance of
half W from the center line, to determine the screw
locations.
5. Fit 4 screws on cabinet bottom do not tighten
completely but leave a space of about 1/2" from
cabinet bottom surface and head screws.
6. Run 10" Duct, long enough to reach the transition
once the hood has been installed plus1 1/2" inch for
connect ductwork.
7. Remove 1 of 2 knockouts and install 1/2"conduit
connector in j-box.
8. Hang the hood on screws through side slots provided
on hood top.Tighten the four screws. Note: If possible
fix the hood on the wall at 4 additional point (2 on
upper side, 2 on lowerside).
9. From the inside of the cabinet attach the transition
on upper outlet.
.
HOOD W IDTH DIM. "W " DIM. "K " DIM. "Z"
30"
36"
35 - 1/16" 2 - 1/2"
48"
47 - 1/16" 2 - 1/2"
Table 3
Figure 4a
Figure 4b
9
29 - 1/8"
2 - 1/2"
7 - 1/16"
7 - 1/16"
7 - 1/16"
Side slot x 4
Center Hole

Advertisement

Table of Contents
loading

This manual is also suitable for:

Hpwb48Hpwb36Hpwb30fsHpwb36fsHpwb48fs

Table of Contents