Appendix B - Rtsx And Rtsd Transfer Switch Installation & Operational Testing - Generac Power Systems GH-410 Installation Manuallines

Air-cooled generators
Hide thumbs Also See for GH-410:
Table of Contents

Advertisement

Available languages

Available languages

14. Switch the main breaker ON to restore utility power.
The generator will continue to run to allow the engine to cool
down before shutting itself off.
Shut off utility power again. The generator should start and the
entire priority load should transfer to the generator.
Close the main breaker to restore utility power and allow the
engine to cool down and shut itself off.
15. Operational tests are now complete. Refer to – Setting the
Automatic Exercise Function to complete the installation.
APPENDIX B – RTSX AND RTSD TRANSFER
SWITCH INSTALLATION & OPERATIONAL
TESTING
1. Before beginning any installation, make sure power is shut
OFF to the main distribution panel and carefully read the
Owner's Manual that came with the transfer switch.
To simplify the installation process, the transfer switch
should be mounted as close to the main distribution panel as
possible. Make sure no water or corrosive substances can
drip onto the transfer switch enclosure.
2. Always inspect the switch for shipping damage. Never mount
a transfer switch that shows any evidence of damage.
3. Protect against impact and mount the switch vertically to a rigid
support structure. Make sure the switch is level and plumb.
Check local codes before wiring the transfer switch. Some
jurisdictions require that wiring inside the switch be done by a
licensed electrician.
4. All wiring must be the correct size and type, and must
conform to all codes, standards and regulations. Refer to the
transfer switch Owner's Manual and the National Electrical
Code for additional information.
Appendix B
15