Siemens Liquid Injection Valve Specifications; Table 4-5 Configuration - Siemens Maxum II PD PA AP Service Manual

Valves and oven components
Table of Contents

Advertisement

Valves
4.2 Liquid Injection Valve
Procedure
1. Check the spring travel and correct using the adjustment assembly (13) if necessary. The
spring travel is correctly set if the flange (17) can be rotated a further 2.5 rotations starting
with the first pressing of the Belleville washer plate springs until the flange rests on the
valve body. The plate springs can be viewed through a hole when pressing together. If the
flange is tightened firmly, there should be a gap of 0.3 to 0.5 mm between the plate springs.
2. If the adjustment is necessary, loosen the flange from the valve body again, and screw the
nut and counternut in or out as necessary. Then repeat the preceding step.
3. This step is only necessary if using the less common cross-hole stem and should only be
executed if the entire valve including the vaporizer is removed from the analyzer.
Rotate the vaporizer (16) using a 6mm wrench until the carrier gas inlet (18) is parallel to
the sample flow unit (15). The carrier gas should flow through the hole in the stem when
injecting.
Installing the SLIV in the Analyzer
1. If the entire valve was completely removed from the analyzer (including the flange and
vaporizer), reinstall it at this time, but do not connect control lines, sample lines, or carrier
gas.
When installing the valve, adjust the valve body (7) so that sample will flow vertically through
the valve. This is necessary to prevent bubbles from forming in the valve.
2. Position the control cylinder (1), and tighten the two hex set screws (2) on the side. The
screws must firmly grip the groove in the valve body (5) wall. See the
Body illustration.
3. Connect the control lines.
4. Activate the actuator pneumatically. Check that you can hear the switching and movement
noises.
5. Connect the sample lines. After connecting the sample lines inspect that they are not
subjected to any strain and that sample will flow through the valve vertically (to prevent
bubbles from collecting in the valve).
6. Complete re-installation of valve into analyzer including reconnection of carrier gas and
column tubing (if these were disconnected during removal).
Replacing the Dosing Stem
Although it is possible to replace the control piston (3) and stem (6) without disassembling the
valve body (7), Siemens recommends that the valve body be disassembled and serviced
whenever the stem is replaced.
4.2.5

Siemens Liquid Injection Valve Specifications

Table 4-5
Valve Type
Vaporization System
44
Configuration
Pneumatically operated piston actuating a moving liquid-injection tappet
Temperature-controlled vaporization system
Liquid Injection Valve
Maxum II Valves and Oven Components
Service Manual, 10/2018, A5E42019844001

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents