Partial flow commercial room ventilator 24 volt on/off with spring return and exhaust. for use with bard single stage wall mount air conditioner and heat pump models: w42ac, w48ac, w60ac, w72ac, w42hc, w48hc, w60hc (17 pages)
Page 1
INSTALLATION INSTRUCTIONS Wall Mount Energy Recovery Ventilator with Exhaust Models: ERV-FA2 ERV-FC2 ERV-FA3 ERV-FC3 For Use with Bard 1.5 – 3 Ton Wall Mount Air Conditioners and Heat Pumps Bard Manufacturing Company, Inc. Manual: 2100-701 Bryan, Ohio 43506 Supersedes: NEW...
It is designed as a single package which can be easily • Installation instructions factory or field installed for new installations or retrofit to the new Bard W**A and W**H series wall-mounted UNPACKING units. The package consists of a unique rotary energy recovery cassette that can be easily removed for Upon receipt of the equipment, be sure to compare the cleaning or maintenance.
1. Unpack the ventilator assembly which includes the integral ventilator with attached electrical harness For Use with the Model Electrical and miscellaneous hardware. Following Units W18AB-A W18HB-A 230/208V ERV-FA2 W24AB-A, -B W24HB-A, -B 1 or 3 phase WARNING 460V ERV-FC2 W24AB-C W24HB-C 3 phase...
4. Remove and save existing unit return air filter. Remove left side filter support bracket by unscrewing two (2) screws from left side of unit. Remove and save top four (4) screws from front grille (see Figure 2). 5. Remove and discard exhaust cover plate (see Figure 2).
6. Insert ventilator into the unit to the far left side, 7. Remove outer and inner control panel covers. making sure to clear the right filter bracket. Once 8. Remove female plug of high voltage wiring harness the ventilator is fully inserted, slide the ventilator (3-pin plug) from the heat recovery assembly to the right until it is tight against the back of the and snap into unit control panel (from inside...
9. Plug low voltage plug (12-pin plug) from the heat 11. Replace inner and outer control panel covers. recovery unit into the front side of the control 12. Ventilator checkout panel (see Figures 3 and 4). A. Resupply power to unit. NOTE: These 24 volt control wires control the starting B.
C. Ventilator heat transfer wheels should rotate 14. Replace the vent option access panel with the new slowly (49 RPM). Intake and exhaust blowers panel provided. Attach air intake hood with screws should run and indoor comfort blower should provided (see Figure 5). Be sure to insert the top run.
When on daily programmed occupancy periods. Bard designing the control circuit for the ventilator, the markets and recommends Bard Part No. 8403- following requirements must be met. 060 programmable electronic thermostat for air conditioner and heat pump applications.
Proper cleaning of the Bard energy recovery The need for periodic cleaning will be a function of wheel will restore latent effectiveness to near original operating schedule, climate and contaminants in the performance.
8. If any belt chirping or squealing noise is present, 3. Rinse wheel thoroughly after application of the apply a small amount of LPS-1 or equivalent dry cleaning solution and allow to drain before re- film lubricant to the belt. installing.