This section explains the procedure for installing and starting up the M7-400
components step by step. Please proceed as described below:
1. Check that the power supply to the rack is correctly dimensioned.
(Chapter 2 and /1/)
2. Plug the interface modules into the FM 456-2 and the EXM 478 expansion
modules.
(Section 2.3)
3. If you want to use an ATM 478 adapter module, you must install the appropriate
short AT module in the ATM 478 before the next step.
(Section 2.4)
4. If appropriate, assemble the FM 456-2 with its expansion modules into a
complete unit before installing in the rack.
(Section 2.5)
5. Switch off the power supply (PS).
6. Fit the pre-assembled module or module assembly onto the rack and secure
with the screws.
(Section 2.6)
7. Insert the key in the operating mode switch.
(Section 2.6)
8. Connect a PG or a PC if necessary to install the system software.
(Section 2.11)
9. Connect the necessary operator equipment and peripherals.
(Section 2.10)
10.Switch on the peripherals.
11. Switch the power supply (PS) on again.
12.Check that the status and fault displays respond correctly.