Figure 5 – Laying the Unit Sideways
To properly lay the unit onto its side:
1. Remove all cabinet panels in order to
prevent damage to them during the
turning process.
2. Attach 4x4 blocks or timbers to the rear
frame to act as support feet while the unit
is in the horizontal configuration.

LOCATION AND CLEARANCES

Particular care must be taken when
placing the machine so as to provide
adequate clearance for access to each
side of the machine.
mostly done through the front of the unit,
but in a repair scenario, any panel on any
side may need to be removed to access
components behind them.
Maintenance is
8
3. Attach two rigging cables to the unit feet
across the front of the unit. Bring these
cables to a single point, maintaining a
minimum of 60° between the unit and the
cable.
4. Attach two rigging cables to the left side
lifting lugs. Bring these cables to a single
point.
5. Attach two rigging cables to the right side
lifting lugs. Bring these cables to a single
point.
6. Using these three points, lift the unit
slightly off the ground, using the lifting
cables on the feet to rotate the unit onto
its back. Use the right and left side lifting
cables to control the sideways rotation.
7. Once the unit is in the horizontal
configuration, let it gently rest on the
blocks that were attached during step 2.
8. Once the unit is to be turned back to the
vertical configuration, it is preferable that
the unit again be lifted and rotated in the
same
manner
as
However, in cases where mechanical
lifting is not available at the installation
site, the unit CAN be lifted up and tilted
over onto its feet.
 Do not let the unit fall hard onto its feet.
 Do not allow the feet to become deformed.
Be mindful of the 1000 pound mass of
the unit.
Human power alone is not
advised as it could cause this to become
a very dangerous and potentially deadly
procedure.
Clearance
Front
Rear
Right
Left
Top
Table 4 – Installation & Service
Clearances
described
above.
Inches
(mm)
40
(1000)
40
(1000)
20
(500)
20
(500)
6
(150)