time, move the breaker to another position.
On flat material such as concrete runways, starting to
break in the middle of the material may cause vibrations
to be transmitted throughout the breaker and excavator
because the material has no place to break to. Always
try to start at a point which will permit the material to
break out.
MAINTAIN DOWN PRESSURE
Maintaining hard contact with the surface of the material
to be broken in addition to maintaining adequate "down
force" is very important. Always keep "down pressure"
or "down force" on the point of the breaker by lifting the
wheels, tracks, or stabilizers slightly above the ground.
This method takes the "slack" out of the bracket and
boom pivots, and reduces the impact on the pivots in
the boom.
The operator needs to be constantly aware of the
amount of down pressure being applied and be able
to adjust it if necessary. Not enough down pressure
results in low production and accelerates wear and tear
on the equipment. Too much down pressure may cause
the breaker housing to violently crash into the broken
material when "break-through" occurs.
In any breaking job, the operator should make every
effort to "follow" the breaker with "down pressure" as the
machine breaks farther into the material. The breaker
should be stopped as soon as "break-through" occurs or
if it is apparent that good, solid blows are not occurring.
BREAKING
The operator should note the sound of the blow when
the breaker is running. With experience, the operator
will be able to tell the difference between a good solid
blow and a hollow sounding blow. A hollow blow means
that solid blows are not occurring and breaker should be
repositioned.
Continuous tool penetration usually does not do much
good. If the material does not break with 3 – 6 inches
of tool penetration, it usually won't break with full
penetration. The time used for additional penetration
could be better used to strike blows in another place.
Many materials do not respond well to continued
hammering in one place. The breaker tool should be
repositioned on the work each time the tool penetrates
but does not crack the material.
16 ► MBF5 User Manual
OPERATION
Continuous penetration in the same area for lengthy
periods will create excessive temperatures at the tip
of the tool bit, resulting in loss of temper (hardness)
of the bit, mushrooming of the tip of the bit and may
Use a "scoring" method of breaking when cracking
the material becomes difficult. This technique involves
striking the rock or concrete at several places along a
line where you want the crack to occur. Most materials
break sooner when struck several places along a line
than when struck repeatedly in one location. On each
line, the breaker tool should be continually repositioned.
Practice determines the best length of time to stay in
one spot (15 – 20 seconds) and how far to move the
breaker tool.
Do not break continuously
in one place.
lead to failure of the bit.
Scoring with the breaker