10060
Operation at generator (at external input)
10061
Feeding network op (at external input)
10100
Parameter [xx] set successfully. [xx] to [xx]
The displayed parameter was successfully changed.
10101
Setting of parameter [xx] failed. |xx| to |xx|
The displayed parameter was not changed.
Corrective action:
10102
Parameter [xx] set successfully. |xx| to |xx|
The displayed parameter was successfully changed.
10103
Setting of parameter [xx] failed. |xx| to |xx|
The displayed parameter was not changed.
Corrective measures:
10104
String parameter set successfully
10105
String parameter setting failed
10108
Time adjusted / old time
10109
Time adjusted / new time
10110
Time synchronization failed: |xx|
10114
No time information could be called up from the set NTP server.
Corrective measures:
10117
Invalid date > Set time and date
System time is invalid.
Corrective measures:
10118
Parameter upload successfully performed
The configuration file was loaded successfully.
10121
Setting of parameter [xx] failed. Device must be stopped first
10122
Setting of parameter Lxx failed. Installation assistant must be started
Operating Manual
• Make sure thresholds of the parameters are complied with.
• Change the parameter again.
• Make sure thresholds of the parameters are complied with.
• Change the parameter again.
• Ensure that the NTP server was configured correctly.
• Ensure that the inverter is integrated into a local network with Internet connection.
• Set the Date and Device Time via the installation assistant.
15 Troubleshooting
SI44M-80H-12-BE-en-10
167

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Sunny island 8.0hSunny island 6.0h

Table of Contents