1. Position the cable guide-left and cable guide-right against the front of the chassis and align the four screw
holes, as shown in the following figure.
2. Secure the cable guides with the four M6x12mm screws supplied with the cable kit. The recommended
maximum torque is 3N-m.
DETAILED STEPS
Step 1
Position the cable guide-left and cable guide-right against the front of the chassis and align the four screw holes, as shown
in the following figure.
Figure 11: Cable Guide Installation For 19-inch Rack Brackets
Figure 12: Cable Guide Installation For ETSI Rack Brackets