11.3.4
Connect the cable to the Outdoor Unit
1
Remove the control board cover from the unit by loosening the screw.
2
Connection cable between indoor unit and outdoor unit shall be approved polychloroprene sheathed 4 × 1.5
2
mm
(3/4 ~ 1.75HP) or 4 × 2.5 mm
cord. Do not use joint connection cable. Replace the wire if the existing wire (from concealed wiring, or
otherwise) is too short.
3
Secure the cable onto the control board with the holder.
4
Attach the control board cover back to the original position with the screw.
5
For wire stripping and connection requirement, refer to instruction
Earth wire shall be Yellow/Green (Y/G) in colour and longer than the other AC wires for safety reason.
11.3.5
Piping Insulation
1
Please carry out insulation at pipe connection portion as mentioned in Indoor/Outdoor Unit Installation
Diagram. Please wrap the insulated piping end to prevent water from going inside the piping.
2
If drain hose or connecting piping is in the room (where dew may form), please increase the insulation by
using POLY-E FOAM with thickness 6 mm or above.
11.3.5.1
Cutting and flaring the piping
1
Please cut using pipe cutter and then remove the burrs.
2
Remove the burrs by using reamer. If burrs are not removed, gas leakage may be caused. Turn the piping
end down to avoid the metal powder entering the pipe.
3
Please make flare after inserting the flare nut onto the copper pipes.
2
(2.0 ~ 2.5HP) flexible cord, type designation 60245 IEC 57 or heavier
WARNING
This equipment must be properly earthed.