61 DhW FLOW TURBINE sENsOR REPLaCEMENT
1. Refer to Frame 49.
2. Remove condensate trap/siphon. Refer
to Frame 59.
3. Lift off the flow turbine sensor plastic
retaining clip.
4. Unplug the electrical connection and
transfer to new turbine sensor.
5. Reassemble in reverse order.
6. Check operation of the boiler. Refer to
Frames 38 & 39.

62 DRaINING ThE BOILER

CENTRaL hEaTING CIRCUIT
1. Refer to Frame 49.
2. Close all the CH water isolating valves on the boiler inlet.
3. To drain the primary heat exchanger circuit: Open the drain
valve and attach a length of hose to the CH drain point.
4. After replacing any component on the boiler, remove the
hose, close the drain valve and open all system isolating
valves (re-pressurise as appropriate by re-connecting the
filling loop, refer to Frame 30) before proceeding to check
operation of the boiler.
5. Disconnect filling loop. Refer to Frame 30.
6. Check operation of the boiler. Refer to Frames 38 & 39.
DOMEsTIC hOT WaTER CIRCUIT
1. Refer to Frame 49.
2. Close all the DHW water isolating valves on the boiler inlet.
3. To drain the domestic hot water circuit: As there is no direct drain for the domestic hot water circuit, depending on the location
of the boiler, opening the lowest hot water tap may drain this circuit. However it must be noted that some residual water will be
experienced during replacement of components.
4. After replacing any component on the boiler, close tap, close the drain valve and open all system isolating valves (re-pressurise
as appropriate by re-connecting the filling loop, refer to Frame 30) before proceeding to check operation of the boiler.
5. Disconnect filling loop. Refer to Frame 30.
6. Check operation of the boiler. Refer to Frames 38 & 39.
63 PREssURE GaUGE RENEWaL
1. Refer to Frame 49.
2. Drain the heating system. Refer to Frame 62.
3. Unscrew the pressure gauge and discard.
4. Fit new pressure gauge, using suitable jointing
compound.
5. Refill the boiler. Refer to Frame 30.
6. Check operation of the boiler. Refer to Frames
38 & 39.
46
sERVICING
CH
Flow
Ideal Logic Combi -
4
Filling Loop
CH
Circuit
Drain
DHW
Gas
DHW
Outlet
Inlet
Return
Installation and Servicing
3
204626-9692d
CH
3G9690

Advertisement

Table of Contents
loading

This manual is also suitable for:

Logic combi 35Logic+ combi 30

Table of Contents