Figure 40 Liebert NX 160-200kVA UPS to 49" battery cabinet interconnection
NOTES:
1. All cables must be repositioned prior to and while setting the cabinets in their installed location.
2. Refer to the individual drawing of each piece of equipment for additional details.
Run
A
UPS Battery Terminal Block
B
External Battery Cabinet
Battery Cabinet(s) Breaker
C
Control Terminal Block
D
C
NX 160-200KVA UPS Module
A
C
B
49" Battery Cabinet Right-Side Views
From
UPS Ground
D
A
Front View
C
D
To
External Battery Cabinet
Additional External
Battery Cabinet(s)
UPS Monitoring Board
Battery Cabinets Ground
66
Installation Drawings
B
D
Conductors
Positive, Negative
Positive, Negative
Battery Breaker
Auxiliary Contacts
Ground
®
™
Liebert
NX