9.3.2
Decision-Makerr 3500 Paralleling Sequence of Operation
Note: Sequence of operation
is for unit-mounted breakers. Additional
steps for remote-mounted breakers are
shown in:
Figure 9-6 Sequence of Operation
TP-6862
6/14
Install generators
Connect circuit
breaker control and
status wiring
Connect bus sensing
Connect output leads
to the paralleling bus
Connect PGEN
communication wiring
All generators in OFF
Confirm dead bus
Start generator 1
using RUN button
Generator
automatically closes
to bus. The breaker
closes, reopens, and
closes again.
Generator operates
without any faults or
warnings
Generator 1 in OFF
Generator 1 in OFF
Repeat for each
generator individually
Place all generators
in AUTO and give
start signal
Follow the instructions provided
earlier in this manual.
Consult the wiring diagrams
provided in the operation manual.
Consult the wiring diagrams
provided in the operation manual.
Consult the wiring diagrams
provided in the operation manual.
See Section 9.3.1 in this manual.
If the engine does not start, consult the
operation manual for troubleshooting
information.
If breaker does not close or reopen,
see Section 9.4.
If faults or warnings are displayed
on the Decision-Makerr 3500
controller, see Section 9.5.
If faults or warnings are displayed
on the Decision-Makerr 3500
controller or if the generator set
does not function correctly, see
Section 9.6.
Section 9 Paralleling Generator Sets
63