2. What needs to be observed during commissioning

Check that the points listed in section 1 ("What needs to be observed before commission-
ing") have been taken into consideration. The following should be carried out in the given
order when commissioning or converting the machine:
1.
Measure the connection pressure. The connection pressure must be within the
ranges specified in EN 437 (see section "Country of destination and category").
2.
Ask the gas supply company what the gas family, gas group and connection pressure
are, and compare this information with the data specified on the machine (see the
sticker at the rear).
3.
Check the factory-set jet pressure based on the sections "Country of destination and
category", "Settings with natural gas" and "Settings with liquid gas" and correct it if
necessary.
4.
If the gas family, gas group or connection pressure is different, it must be converted
as instructed in the section entitled "Connection and conversion instructions" and the
sticker at the rear of the machine must be replaced.
Set the jet pressure at the machine's gas regulating valve (see "Settings with natural gas"
or "Settings with liquid gas" section).
If the gas family needs to be changed, please request the appropriate conversion kit
from the Miele Customer Service Department. When doing so, please specify the
product name and the machine number, as well as the gas family, gas group, gas con-
nection pressure and country where the machine has been set up.
5.
Switch on all gas consumers that are present, including the installed appliance.