Fujitsu and Fujitsu Customer Use Only
3
Commissioning Test
3.1
Overview
3.2
Preparation
Station and Hop Test Items
Table 3.2.1 Antenna Alignment & Commissioning Test Items
Task Name
Preparation
DC Power Supply ON
Open WebLT
Antenna Alignment
TX power setting
Antenna alignment
Continuity Test
Signal continuity Tests
Performance monitoring
Measuring Instrument Required
BroadOne GX40000 Manual (R3.0) issue 1.03
This chapter explains the antenna orientation and how to do the commission
test for the GX4000 link. Main topics covered are;
Preparation
Antenna alignment guideline
Antenna alignment procedure
Continuity tests after antenna alignment
Configuration setting (Provisioning)
The following safety precautions must be observed when installing, using, or
maintaining radio equipment. These precautions ensure the safety of all
personnel and the protection of radio equipment.
Section 3.3
Section 3.4
Section 3.5
Section 3.5
Section 3.6
Section 3.6
Note:
In case that test result is out of specification, please refer to Chapter 4
Maintenance and trouble shooting.
The typical measuring instrument required to carry out the commissioning
tests are as follows;--
Multi-meter for power supply voltage and antenna alignment test
PC for configuration setting & performance monitoring
Manual Reference
Commissioning Test
Notes
3-1