The second fold table should always be installed into the cavity beneath the feed table
(see photo 1). However, depending on the style of fold that is being done it can be
installed two ways. The aluminum deflector on the second fold table should be installed
facing the unit when there is going to be only one fold in the sheet. This is illustrated in
photo #2.
However, if there is going to be two folds in the sheet the aluminum deflector should
be facing out. To engage, simply position the table so that the two tie rods in between
the side frames of the machine will be in the cut-out grooves on the bottom of the fold
table (see photo #2). It is important that this is done because if the table is not properly
positioned, the machine will produce jams and inaccurate folds.
When installing the
second fold table for
a tri-fold, it should
be put in so that the
open end faces the
machine
abcoffice

SECOND FOLD TABLE INSTALLATION

Photo 2
When setting the folds for
the unit, be careful not to
over tighten the adjustment
knobs on the paper stops.
Martin Yale Industries, Inc.
251 Wedcor Avenue
Wabash, IN 46992
Info@martinyale.com
800-658-8788
Photo 1
When installing the
second fold table for a
half fold, it should be
put in so that the
deflector end faces
the machine.