Preliminary Start-Up Steps

Check for proper fuel-supply application, connections, and pressure.
Check that external regulator has been installed on all natural-gas installations over 4-psi.
External regulator must be installed on unit on all propane installations.
Purge gas line of air, as necessary.
Leak test all gas connections with a 1:3 solution of soap and water.
Do not operate unit if leaks are present.
Determine that unit is drawing 100% fresh outside air through its intake grill.
Check for proper electrical connections and supply voltage.
Check that the intake and discharge of unit are free from obstructions.
Reset flame-safety control by pressing reset button on control.
Reset motor overload.
Check control settings:
high-temperature limit switch: 270° F
low-temperature limit switch:
THP-400A Switch Panel
THP-500A Switch Panel
40° F
Note: Other switch panel layouts may be
used depending on application.
TEMP-HEAT
®
THP-550 Switch Panel
9