Figure 7.14.: Install Settings Page - Installer Mode
Inverter ID: This setting is used to set unique ID's for installations with more than one
inverter. In a multi-inverter installation where the inverters will be in a network, each inverter
must have a unique ID.
Insulation: ON means enable the measurement of impedance between Array and PE, will
not connect to Grid if failure. Depending on DC wiring conditions, user can set 6 kinds of
insulation detecting methods - ON, Positive Ground, Negative Ground, DC1 only, DC2 Only,
or Disable. Installer can select different resistance criteria according the actual conditions.
Country: This is the Country selected during startup (nonadjustable).
Figure 7.15.: Insulation Settings - Installer Mode

Active/Reactive Power control for DE LVD and DE MVD

7.3.6.3
Below is an overview of the features that are adjustable to control the production of active and
reactive power for Germany LVD and MVD
Feature
Active power control
available for
LVD
MVD
Operating the PV inverter
Description
EN
63