New Horizon BioMass NextGen 25 Owner's Manual

Wood gasification boilers

Advertisement

BioMass
Wood Gasification Boilers
Distributed exclusively in North America by:
Owner's Manual
Model 25
Model 60
UL/CSA approved by GUARDIAN
NextGen
New Horizon Corporation, Inc.
151 McGregor Drive
Sutton, WV 26601
(304) 765-7171
newhorizon@gmail.com
www.newhorizoncorp.com
- 1 -
Model 40
Model 80

Advertisement

Table of Contents
loading

Summary of Contents for New Horizon BioMass NextGen 25

  • Page 1 NextGen BioMass Wood Gasification Boilers Distributed exclusively in North America by: New Horizon Corporation, Inc. 151 McGregor Drive Sutton, WV 26601 (304) 765-7171 newhorizon@gmail.com www.newhorizoncorp.com Owner’s Manual Model 25 Model 40 Model 60 Model 80 UL/CSA approved by GUARDIAN - 1 -...
  • Page 2 - 2 -...
  • Page 3: Table Of Contents

    Boiler parts and features ......... 12 Open system setup ..........14 Electrical setup for Model 40 ........15 Electrical setup for Model 60 ........16 Manufactured for New Horizon Inc. by: "HAMECH"- POLAND 17-200 HAJNÓWKA ul. Armii Krajowej 3 tel. 85 682 20 21 do 26...
  • Page 4: General Information

    Failure to install or operate the boiler as described in this manual will void the warranty. BioMass boilers should be installed by a certified plumber or plumbing and heating contractor or technician. New Horizon Inc. does not take any responsibility for incorrect installation or improper boiler usage.
  • Page 5: Fuel Sources

    1. Fuel sources The recommended source of fuel for the BioMass boiler is cut and split firewood that is well seasoned, with moisture content between 15% and 30%. Log size should be around 6 inches in diameter and about 20 inches in length for the BioMass 40 and up to 30 inches in length for the Model 60.
  • Page 6: Specifications Diagram

    For ease of operation, the BioMass is equipped with an RK2001UA-D controller, which is located on the top of the boiler and clearly visible and accessible from the front of the boiler. Function of the Controller: 1. Reach operation temperature (pre-set on dial) by operating variable speed blower 2.
  • Page 7: Technical Information And Specifications

    Technical Info Models BioMass Rated Power Output European Standard 303-5 Fuel Moisture Level Cord of Wood – with a maximum of 35% moisture Power Range 40-85K BTU 50K – 145K 60K – 215K 120K – 300K Efficiency 91.2 Possible Fuels Seasoned Wood, Briquettes, Corn Cobs with Kernels, 50% of Coal, Saw Dust, Wood Chips (50%), any kind of pellets Temperature...
  • Page 8: Rk2001Ua-D Controller Operation

    RK2001UA-D controller operation Before connecting the RK2001UA-D regulator to an electrical circuit, always follow these safety precautions: • Make sure that all the safety covers are in their appropriate place; • Make sure that the electrical wires do not come in contact with any hot part of the boiler and the length of the wires used is sufficient;...
  • Page 9: Boiler Operation

    4. Boiler operation Before firing the boiler up for the first time: • Please read the entire owner’s manual; • Confirm that your entire hydronic heating system has enough water; • Confirm that the boiler is connected to the correct power source; •...
  • Page 10: Additional Maintenance Tips

    heat exchanger unscrew the access side panel (23) on the side of the boiler, and access panel (22); remove the ash by sweeping it away and close up the panels periodically. Removing ash from the gasification chamber (bottom) normally should be done once every 7-10 days, depending on the moisture content of the wood and amount of wood burned.
  • Page 11: Hot Water Storage Tank

    IMPORTANT! The BioMass boiler should be installed by a licensed or certified heating professional. The BioMass boiler should have a backup power system to prevent overheating in the event of a power outage. The simplest arrangement consists of an inverter (350 W computer power backup) and a marine battery connected to the inverter to increase operating time.
  • Page 12: Recommended Clearances

    Recommended clearances for BM 25,40,60,80 (in mm) Note: Neither New Horizon Corp. nor the manufacturer is responsible for inappropriate boiler installation or operation. - 12 -...
  • Page 13: Boiler Parts And Features

    Boiler parts and features (See page 13 for details) - 13 -...
  • Page 14 1.Controler RK 2001UA-D 15.Flue Connection 6” 2.Upper Door 16.Clean-up Access Cover 3.Loading Chamber (gasification) 17.Clean-up Access 4.Combustion Air Flow (primary) 18.Chimney Bypass Flap 5.Primary Air Adjustment 19.Heat Exchanger Clean-up Lever 6.Blower Housing 20.Overheat Thermostat 7.Air Mixing Box 21.Hot Water Outlet 8.Blower (for BioMass 60) 22.Lower Clean-up Access Cover 9.Blower Air Adjustment...
  • Page 15: Open System Setup

    Open system setup example - 15 -...
  • Page 16: Electrical Setup For Model 40

    Electrical setup for BioMass 40 - 16 -...
  • Page 17: Electrical Setup For Model 60

    Electrical setup for BioMass 60 and 80 - 17 -...
  • Page 18 – USA and CANADA New Horizon Incorporated (Importer) warrants the residential steel boiler identified below and the hot water tank or coil, and the cast iron doors and grates against defects in material and workmanship under normal home use and...
  • Page 19 This warranty shall not be construed as inconsistent with any federal, state or municipal law or any regulations promulgated in connection herewith. Questions regarding this warranty may be referred to New Horizon Corporation,Inc. 151 McGregor Drive Sutton, West Virginia 26601 newhorizoncorp@gmail.com...

This manual is also suitable for:

Biomass nextgen 40Biomass nextgen 60Biomass nextgen 80

Table of Contents