Section 3.3 Installing the Cell
Lay out equipment pieces to be sure there is enough pipe space between the last piece of apparatus and
the tees in the return line to fit the Flow Sensor and the Cell. A Vertical Installation may be used to save
space.
1.
The Cell and Flow Sensor must be installed
downstream from the filter and heating
devices but before any tees in the return
line. The Cell may be installed horizontally
or vertically so long as the Cell is pointed in
the direction of flow and is installed
immediately after the enclosed Flow Sensor
(see diagram above).
2.
Approximately 15 inches (~380 mm) of available pipe length will be needed for horizontal
installations of the Flow Sensor and Cell. Vertical installations can be made to take less space.
3.
On the pipe where the cell will be installed, mark two lines 11 3/4 inches (300mm) apart and cut out
using hacksaw or pipe cutters.
4.
Unscrew and remove the barrel unions (i.e. barrel nuts and slip connections) from either end of the
Cell. Thread one of the barrel nuts over the pipe and glue its slip connection to the cut pipe.
5.
Hold up the Cell with the second union to gauge the proper distance before threading the second nut
and gluing the second slip.
6.
After the glue had sufficient drying time, place the Cell with the o-rings into the opening between
the two ends of the pipe and tighten the unions making sure that the Cell is installed with the arrow
pointing in the same direction as the flow (i.e. water should enter from the side with the blue cap).
NOTE
Flow direction
Page 4