Redback SB9600 Installation Manual

Smart battery systems
Table of Contents

Advertisement

Quick Links

Installation Manual
SB7200/SB9600/SB14200 Smart Battery Systems
v1.32

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the SB9600 and is the answer not in the manual?

Questions and answers

Summarization of Contents

Know Your Product
Major Components Overview
Details the main physical components of the Smart Battery system, including enclosures, modules, and batteries.
Status Panel LEDs
Explains the system status indicators on the front panel of the Smart Battery.
BoS Switchgear
Describes the switchgear components and their function for isolating power.
EMS LEDs Indicators
Details the LEDs on the Energy Management System (EMS) for diagnostic information.
Dimensions, Weights, and Configurations
Provides physical specifications and dimensional data for different Smart Battery models.
Compatibility and Limitations
Outlines system compatibility, unsuitable applications, and operating restrictions.
Backup Circuit Design Notes
Explains the limitations and suitable loads for the Smart Battery's backup circuit.
Installation
Important Safety Instructions
Crucial safety guidelines for installing electrical power systems, emphasizing caution and qualified personnel.
Symbols and General Safety
Explains symbols used elsewhere in the manual and provides general safety precautions.
Battery and Equipment Safety
Details critical safety warnings for battery handling and equipment operation to prevent hazards.
Installation Overview
Provides an overview of the installation process, requirements for installers, and pre-site preparations.
On-Site Installation Checks
Covers on-site checks including Wi-Fi, location review, hardware, electrical, and commissioning steps.
AS/NZS5139 Installation Requirements
Details compliance requirements for battery system installations based on AS/NZS5139 standards.
Preliminary Electrical Installation
Covers the initial steps for running AC, backup, and communication cables before system installation.
Installing the Battery Enclosure
Step-by-step guide for installing the battery enclosure, including pre-assembly and safety warnings.
Battery Enclosure Installation Process
Details the process of physically mounting and securing the battery enclosure to a wall.
Battery Installation and Preparation
Covers installation notes, safety precautions, and preparation steps for the batteries.
SB7200 Battery Connection
Detailed procedure for installing and connecting batteries for the SB7200 model.
SB9600/SB14200 Battery Connection
Detailed procedure for installing and connecting batteries for the SB9600 and SB14200 models.
SB9600/14200 DC Power and BMS Schematics
Provides schematic diagrams for DC power and BMS connections for SB9600/14200 models.
BMS Module Installation
Guides the installation of the Battery Management System (BMS) module and its connections.
Installing the Inverter Module
Step-by-step instructions for mounting the inverter module onto the battery enclosure.
AC Cable Preparation and Sizing
Details AC cable sizing requirements and procedures for preparing grid and backup AC cables.
Communication Cable Preparation
Instructions for preparing Ethernet, Energy Meter, DRED, and Relay cables for system connection.
Complete Inverter Module Installation
Final steps for completing the inverter module installation, including fitting covers and retainer brackets.
Smart Battery External Connections
Diagram and explanation of external AC and communication cable connections to the Smart Battery.
SM3000 Meter Installation
Instructions for installing the SM3000 energy meter, including overview and site preparation notes.
AC-Coupled Configuration
Details the connection of the SM3000 meter for AC-coupled systems.
Standalone Configuration
Details the connection of the SM3000 meter for standalone systems.
Relay Connections and Setup
Explains how to connect and configure Redback RK-1 Relay Kits for load control.
Relay Configuration Notes (Software)
Provides guidance on configuring relays using the RedbackINSTALL app and portal.
Commissioning
Commissioning the Smart Battery
Procedures for initial startup and commissioning of the Smart Battery system.
Connect RedbackINSTALL App
Steps to connect the RedbackINSTALL mobile app to the Smart Battery via Bluetooth.
Onboarding and Network Connection
Guides the process of connecting the Smart Battery to the local network (LAN or Wi-Fi).
Regional Safety Settings
Explains the mandatory selection of regional safety settings for system operation and compliance.
Firmware Version Identification
Methods to identify the Smart Battery's firmware version using RedbackINSTALL app and the Redback Portal.
Compliance Inspections
Details the process of assigning a compliance inspector through the Redback Portal.
Compliance Inspection Process
Describes how nominated inspectors view settings and confirm compliance via the Redback Portal.
Troubleshooting
Shutdown Procedure
Step-by-step instructions for safely shutting down the Smart Battery system.
Restart Procedure
Detailed steps for restarting the Smart Battery system after a shutdown.
Earth Fault Alarm
Describes the procedure for an earth fault alarm and its indication.
Inverter Status LEDs
Explains the meaning and solutions for various LED indications on the inverter status panel.
EMS Status LEDs
Details the status and meaning of the Energy Management System (EMS) LEDs for troubleshooting.
SD Card Replacement
Procedure for replacing the MicroSD card containing the Smart Battery software and settings.
Maintenance
Routine Maintenance Checks
Covers annual maintenance tasks for the battery enclosure, inverter, and connections.
Specifications
Product Specifications
Detailed technical specifications for the SB7200, SB9600, and SB14200 models.
Close-up and Handover
Close-up Procedures
Final steps after commissioning, including fitting covers and cleaning the worksite.
Homeowner Handover
Guidance for explaining the installation to the homeowner and providing documentation.